Re: Summary Progress bar by John
John
Wed Jul 07 20:53:36 CDT 2004
v,
The value you see, Summary Progress (date), is a calculated value and
does not exist as a separate field. I played with it a bit but could not
determine exactly how Project is calculating the value. At first I
thought it was simply a date determined by adding Summary line Duration
* Summary line % Complete to the Start date, but it doesn't pan out. I
would have to work on it some more to find out how Project calculates
the Summary Progress date. Once the formula is determined, it would be
possible to put this value into a spare field (e.g. Date1).
I know this doesn't help much. Is there a reason you want to show this
value in a separate field?
John