Re: Status of summary tasks incorrect by John
John
Tue May 20 22:27:29 CDT 2008
In article <ABF2262A-4EB4-4A90-ACAC-0E78F7619E81@microsoft.com>,
Richard <Richard@discussions.microsoft.com> wrote:
> Hi John, orginal post said tasks that are complete, on shedule or future
> task. I am not quite following how the timephased calculation works for
> summary tasks. By my way of thinking a summary task should not show a late
> status unless at least one of the subtasks is showing a late status? What is
> that I am missing?
Richard,
It's been awhile since I analyzed the requirements of the Status field.
However, I do recall, that the status of a summary line tracks the
calculated status of the subtasks. In other words, if one or more
subtasks is late, then the summary shows late, unless one of those
subtasks is a milestone (0 duration). The calculated status of each
subtask is determined by the status date and the cumulative percent
complete. And yes, it can be kind of confusing.
Maybe it would help if I could take a look at your file, or at least a
representative sample that shows the issue. If you're game, zip the file
and send it to me at the address below. I will ask a few questions.
John
Project MVP
jensenljatatfastmaildotdotfm
(remove obvious redundancies)
>
> "John" wrote:
>
> > In article <7A58B459-770C-4A63-B2B1-8204BC575D4B@microsoft.com>,
> > Richard <Richard@discussions.microsoft.com> wrote:
> >
> > > Thanks for the reply John. The status date is set to today and the
> > > cumulative
> > > percent complete looks right , but the status still says late. I can
> > > force it
> > > to say complete by marking all subtasks as 100% complete anything less
> > > than
> > > 100% complete for all the subtasks then the summary task will show late,
> > > many
> > > of the sub tasks are months out in the future. Let me know if you have
> > > any
> > > other ideas.
> > >
> > > Thanks for your help
> > > Richard
> >
> > Richard,
> > Wait a minute, your original post said all subtasks are showing complete
> > but the summary is showing "late". Now your saying you can make the
> > summary show "complete" by making all subtasks complete. Did I miss
> > something?
> >
> > You say the cumulative percent complete "looks right", but does it meet
> > the requirements spelled out by the help file? Use the Task Usage view
> > and set the timescale to show hours. You might want to use a three tier
> > timescale with week and day on the upper two tiers so it's easier to see
> > what day your looking at.
> >
> > John
> > Project MVP
> > >
> > > "John" wrote:
> > >
> > > > In article <2EB8F733-40B1-43CD-837A-1B931390FD21@microsoft.com>,
> > > > Richard <Richard@discussions.microsoft.com> wrote:
> > > >
> > > > > Hi, I am using the standard status field in MS project, the summary
> > > > > task
> > > > > shows the status as late when all of the sub tasks are showing
> > > > > Complete ,
> > > > > on
> > > > > shedule or future task, none are showing late.
> > > > >
> > > > > Can anyone tell me what I need to do to get the status of the sumary
> > > > > task
> > > > > to
> > > > > show the corect status.
> > > > >
> > > > > Richard
> > > >
> > > > Richard,
> > > > Without seeing your actual file, I don't have a ready answer for what
> > > > you are seeing. Try the following. Hover your mouse over the column
> > > > heading for the Status field. In a moment the help file for the Status
> > > > field will appear. Take a look at the definitions Project uses for
> > > > assigning the various status designations. My guess is, you will see a
> > > > problem with the cumulative percent complete for the summary line
> > > > versus
> > > > the status date.
> > > >
> > > > Hope this helps.
> > > > John
> > > > Project MVP
> > > >
> >