RE: Status date by Saviz
Saviz
Mon May 21 20:23:02 CDT 2007
Thanks,
I think the approach you mentioned is better than using status date. Using
status date changes dates etc...and it is very time consuming to find where
all the changes have occured. I prefer like you said not using the Status
date and instead using the current date to perform individual task updates.
Of course in a perfect would using the update features of project would be
helpful, however thing rarely go as planned in project so I really dont
understand the value of using Status date for roject with hundreds of tasks.
Enough of writing :)...have a nice day.
--
Saviz
"Pratta" wrote:
> Hi Saviz
> Why use Status Date? As, as soon as you insert a date in for Status Date,
> Project will then status from that date on a Tools>Update Project or a
> Reshedule Task.
> Try leaving Status Date as NA and set Current Date to status your project
> from the timesheet end-of period.
> --
> Pratta
>
>
> "Saviz" wrote:
>
> > Hi,
> >
> > Is there a way to show the status without updating the schedule (moving taks
> > etc)?
> >
> > I have a situation where I am only interested in displaying the Status line
> > for presentation purposes, yet the MS Project 2003 keeps updating the
> > schedule automatically.
> >
> > I donâ??t have the options Move end â?¦Move start in calculation selected.
> >
> > Thanks,
> >
> > --
> > Saviz