Mike
Fri May 16 10:21:23 CDT 2008
You're welcome, Earl :-)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
"Earl" <ejjohnson@colpipe.com> wrote in message
news:3E6A6625-75DE-4B43-8C39-DF5A6A0959B1@microsoft.com...
> Thanks Mike, your response (and Roland's) was very helpful. I've added
> Baseline Start and Baseline Finish columns to my chart and can now see my
> progress. Thank you both again!
>
> Earl
>
> "Mike Glen" wrote:
>
>> Hi Earl,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> The Start field is the planned date and Project assumes the Actual Sart
>> you
>> enter is the truth and thus overwrites the Start date, thus giving a true
>> record of what is going on. If you want to preserve the original plan,
>> you
>> must save a baseline and then you can use the Tracking Gantt view to
>> compare
>> Actual with Plan. You might like to see my tutorials on tracking.
>>
>> FAQs, companion products and other useful Project information can be seen
>> at
>> this web address:
http://project.mvps.org/faqs.htm
>>
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>> See
http://tinyurl.com/2xbhc for Project Tutorials
>>
>>
>> Earl wrote:
>> > I'm a relatively new user to MS Project 2007, but have created a nice
>> > Gantt Chart for my project complete with Start and Finish dates. I've
>> > inserted Actual Start and Actual Finish columns into my chart, but
>> > whenever I try to updated the Actual Start date for a task, it
>> > changes the Start date.
>> >
>> > For example, if my Start date for a task was April 1, but I enter the
>> > Actual Start date as April 2, my Start date changes to April 2. Note:
>> > The Start date is actually more like a scheduled start date, and it
>> > seems like tracking my progress would be difficult if the Start and
>> > Actual Start dates match up.
>> >
>> > What am I missing?
>> >
>> > Thanks.
>> > Earl
>>
>>
>>