I'm a relatively new user to MS Project 2007, but have created a nice Gantt
Chart for my project complete with Start and Finish dates. I've inserted
Actual Start and Actual Finish columns into my chart, but whenever I try to
updated the Actual Start date for a task, it changes the Start date.

For example, if my Start date for a task was April 1, but I enter the Actual
Start date as April 2, my Start date changes to April 2. Note: The Start date
is actually more like a scheduled start date, and it seems like tracking my
progress would be difficult if the Start and Actual Start dates match up.

What am I missing?

Thanks.
Earl

RE: Start vs. Actual Start??? by Pat

Pat
Fri May 16 10:31:01 CDT 2008

In order to keep track of initial planned dates, you first need to save a
Baseline (Tools, Tracking, Save Baseline).

Pat.

"Earl" wrote:

> I'm a relatively new user to MS Project 2007, but have created a nice Gantt
> Chart for my project complete with Start and Finish dates. I've inserted
> Actual Start and Actual Finish columns into my chart, but whenever I try to
> updated the Actual Start date for a task, it changes the Start date.
>
> For example, if my Start date for a task was April 1, but I enter the Actual
> Start date as April 2, my Start date changes to April 2. Note: The Start date
> is actually more like a scheduled start date, and it seems like tracking my
> progress would be difficult if the Start and Actual Start dates match up.
>
> What am I missing?
>
> Thanks.
> Earl