RE: Splited task - false progress by sai
sai
Fri Mar 14 22:36:00 CDT 2008
Dear Andis,
Thanks for your feedback.
As per your statement ".. Changing the project status date didn't bring any
change." is because "Status Date", by default, is NA and needs to set in the
Project Information form (Project > Project Information ...)
Please let us know if this helps.
Regards
Sai [PMP]
"Andis" wrote:
> Sai,
>
> Thanks, the info was usefull - I didn't know that Project identifies the
> tasks that are on-schedule, and behind schedule.
> My progress line was right in the middle of the split. As soon as i set the
> progress line date that crossed the second part of the task it straightened
> up and the chart looks OK. Changing the project status date didn't bring any
> change.
>
> thanks again,
> --
> Andis Gigulis
> Water Ser Ltd.
> Project manager
>
>
> "B Sai Prasad [PMP]" wrote:
>
> > Dear Andis,
> >
> > I understand your requirement as the progress line stays at the end of first
> > part of the split task, though the actual progress of the split task is more.
> >
> > Progress lines are displayed based on the options and details set in
> > Progress Lines dialog box
> > 1. If you have checked "Always display current progress line", then check if
> > the project status date or project current date in Project Information is
> > correct.
> > 2. If you have checked "Display selected progress lines", then check the
> > date listed under Progress Lines dates list.
> >
> > Based on the date selected (either in 1 or 2), Microsoft Office Project
> > identifies the tasks that are on-schedule, and behind schedule.
> >
> > My guess is the status date or current date in Project Information is before
> > the second part of the split task.
> >
> > Please let us know if this helps.
> >
> > Regards
> > Sai [PMP]
> >
> >
> > "Andis" wrote:
> >
> > > Hi there,
> > > i've splitted a task and added a progress complete which reaches the second
> > > part of the task, but when I add a progress line it still stays at the end of
> > > part 1 of the task despite the actual progress is bigger. In this case the
> > > visual progress line gives a false view.
> > > Thanks in advance
> > > --
> > > Andis