IanColettiPMP
Tue Jun 21 11:07:04 CDT 2005
Mike,
I've seen this before... I saved the baseline in each sub project separately
and then added to the master schedule. The Baseline data doesn't seem to
show at the Summary level (outline level 1) for each sub project. I think
this is a bug! Any thoughts?!?
Thanks!
Ian
"JulieS" wrote:
> Hi Melanie,
> I just tried your scenario - Master Project with inserted projects and
> sadly, got the same result. I was able to save the baseline for the subtasks
> in the project by selecting all tasks (click on the column heading). Go to
> Tools>Tracking>Save baseline, choose selected tasks and check off the two
> options under Roll up baselines.
> This works, but why the first method didn't I don't know.
>
> Hope this helps. Let us know how you get along.
> Julie
>
> "Melanie" wrote:
>
> > Hi Mike,
> > Thank you for your reply!
> >
> > I am using MS Project 2003 Standard. I am working with a Master schedule,
> > i.e. I have several schedules consolidated into one. I am trying to set a
> > baseline for a huge initiative that has already begun (several tasks are
> > partially complete). There is a change initiative project team that will be
> > monitoring all the sub-projects and reporting to the executives.
> >
> > I used mouse clicks, that is I went to Tools/Tracking/Save Baseline... I
> > saved baseline under "Baseline" since it was my first time saving the
> > baseline. The "For:" option was set to "Entire Project."
> >
> > Then I clicked OK.
> >
> > Then in the entry table I inserted the column "Baseline Start" and "Baseline
> > Duration." The only data viewable in these columns is "NA" in all cells
> > except for at the summary task level. Are the lowest level tasks not
> > baselined? Also, when I look at the gantt bars in the Tracking Gantt view, I
> > do not see the the baseline bar next to the task bar, even for the summary
> > tasks that do have some data saved.
> >
> > Am I missing something? Am I expecting something that won't be available?
> >
> > Thanks,
> >
> > Melanie
> >
> > "Mike Glen" wrote:
> >
> > > Hi Melanie,
> > >
> > > Welcome to this Microsoft Project newsgroup :)
> > >
> > > What steps did you take to baseline (key presses or mouse clicks?). What
> > > version of Project are you using?
> > >
> > > FAQs, companion products and other useful Project information can be seen at
> > > this web address:
http://www.mvps.org/project/
> > >
> > > Hope this helps - please let us know how you get on :)
> > >
> > > Mike Glen
> > > MS Project MVP
> > >
> > >
> > >
> > > Melanie wrote:
> > > > I saved a baseline, but no data was saved to the baseline fields.
> > > > What can I do to make this happen?
> > >
> > >
> > >
> > >