i am trying to print the above report from a resource pool i have set up. it
will only show two days on the report? any suggestions?

Re: Resource Usage Report by JulieS

JulieS
Wed Mar 12 07:50:08 CDT 2008

Hello essie88,

Open the pool file with the third option (Open resource pool read-write
and all other sharer files into a new master project file.) Then run
the Resource Usage Report from the master project file.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"essie88" <essie88@discussions.microsoft.com> wrote in message
news:3DAE9C25-54AC-40B7-96A5-C7F97F9AA038@microsoft.com...
>i am trying to print the above report from a resource pool i have set
>up. it
> will only show two days on the report? any suggestions?