A colleague of mine has assigned resources to a project in Project 2003.
They're working a 6 hour workday and assigned to a task at 50%. The
resources should be working on the task for 3 hours a day but Project shows
them at 3.9 hours a day. I have asked my colleague some questions that were
obvious to me. My group is new to Project 2003. I've worked a lot with
Project 2000 (and Project 98 before that). Any ideas?

Re: Resource Problem by Jan

Jan
Mon Aug 22 10:16:48 CDT 2005

Hi,

Your colleague can read
http://www.mvps.org/project/faqs.htm
Faq 5. Default working hours
I'm pretty sure this will help him solve it.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"darryl" <darryl@discussions.microsoft.com> schreef in bericht
news:9C94BC6A-22DB-4DFF-97E3-222EC902097E@microsoft.com...
> A colleague of mine has assigned resources to a project in Project 2003.
> They're working a 6 hour workday and assigned to a task at 50%. The
> resources should be working on the task for 3 hours a day but Project
shows
> them at 3.9 hours a day. I have asked my colleague some questions that
were
> obvious to me. My group is new to Project 2003. I've worked a lot with
> Project 2000 (and Project 98 before that). Any ideas?