Rod
Wed Dec 12 11:06:45 PST 2007
When you track progress you need to update Actual Start and Finish dates.
There should be no completed work in the future and no incomplete work in
the past. Doing this will solve your problem.
--
Rod Gill
Project MVP
Project VBA Book, for details visit:
http://www.projectvbabook.com
NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx
----------------------------------------------------------------------------------------------------
"shooter27" <shooter27@discussions.microsoft.com> wrote in message
news:C490E9A5-A151-448D-B7F7-B43582FEEDC8@microsoft.com...
> When I use a project schedule that has not been resource leveled and when
> I
> go into the Resource Graph, it shows the resources that are overallocated
> in
> certain time frames - which is as designed. I prefer not to resource
> level.
> However, when tasks are marked as completed, they remain on the Resource
> Graph. Especially for time frames when overallocation exists, it would be
> great if the overallocation would disapper for those task that have
> allready
> been completed. Is there a way for the Resource Graph to only show
> incomplete tasks?