Re: Report -weekly totals grouped by a custom field Text1 by Rod
Rod
Sat Jul 01 00:12:56 CDT 2006
You can only get weekly totals for data that is timephased (can be seen in
the Usage views). Have you tried viewing a Usage view then selecting
Project, Group?
You will need to copy Task level Text1 data down to Assignment Text1 level.
--
Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
"Shalini" <Shalini@discussions.microsoft.com> wrote in message
news:0DE0586A-B117-4A1E-87CE-765E2644B920@microsoft.com...
>I need to generate a report from MS projects that gives me weekly totals
>that
> are gouped by data in the Activity column. Activity is a custom field of
> type
> text1.
>
> Anyone has any idea or suggestions.