Hello All,

I am making a plan in which I set the leveling to manual. There are few
tasks in which the successor tasks start before the completion of
predecessor and I manually assigned the day usage via going to "Resource
Usage" for resources. Doing this make the resource overallocated even they
are well leveled and 100% allocated (i.e. 1 day). Can someone help me on
this? One way to avoid it is to level resources via "Automatic leveling"
option but this will shift the schedule ahead of delivery date.

Thanks in advance.

Regards,

Abid

Re: Removing resource overallocation by Mike

Mike
Thu Apr 19 07:45:51 CDT 2007

Hi Abid,

Welcome to this Microsoft Project newsgroup :-)

You might like to see FAQ Item: 34 Overallocations...
FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

"Syed Ali Abid" <aliabid@gmail.com> wrote in message
news:OuF0ECmgHHA.3796@TK2MSFTNGP02.phx.gbl...
> Hello All,
>
> I am making a plan in which I set the leveling to manual. There are few
> tasks in which the successor tasks start before the completion of
> predecessor and I manually assigned the day usage via going to "Resource
> Usage" for resources. Doing this make the resource overallocated even they
> are well leveled and 100% allocated (i.e. 1 day). Can someone help me on
> this? One way to avoid it is to level resources via "Automatic leveling"
> option but this will shift the schedule ahead of delivery date.
>
> Thanks in advance.
>
> Regards,
>
> Abid
>