I have a task that has 4 people allocated at 25% each. Planned work is 100
hours for each resource and they have all tracked 25 hours of actual work on
the task. Resource-a got moved to a special assignment on another project and
needs to be removed from this task. I want to retain resource-a's actuals and
have the remaining planned work redistributed to the other three resources at
33% each. In general, how should this be done?

Thanks

Mike Kleiman

Re: Removing Resource from multi-resource task by Rod

Rod
Thu Mar 13 16:21:02 CDT 2008

Select Window, split then select the task form in the lower pane and
right-mouse click and select Resource Work. Now set remaining work for the
resource to zero and make sure Actual work reflects what they have already
done. Give the remaining work you removed to the other resources.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"Mike Kleiman" <MikeKleiman@discussions.microsoft.com> wrote in message
news:78989205-9F44-41E7-994D-489408B63F34@microsoft.com...
>I have a task that has 4 people allocated at 25% each. Planned work is 100
> hours for each resource and they have all tracked 25 hours of actual work
> on
> the task. Resource-a got moved to a special assignment on another project
> and
> needs to be removed from this task. I want to retain resource-a's actuals
> and
> have the remaining planned work redistributed to the other three resources
> at
> 33% each. In general, how should this be done?
>
> Thanks
>
> Mike Kleiman