Hi,
when looking at the 'remaining work' of a resource which is assigned to
more then one project, the number is different if all his projects are open
or not.
That is the way it should be? can't i know the remaining work of a resource
unless i open all his projects?

Thanks

Re: Remaining work in Resource usage view. by JulieS

JulieS
Mon May 21 17:11:49 CDT 2007

Hello asuchi,

An assumption:. You are working with a resource pool file which is
providing resource to several project files. You are not using Project
Server.

When you open a project file, you should see a message asking if you
want to "...open the resource pool file to see assignments across all
sharer files."

If you select the option to open the pool, you should see remaining work
for all assignments for the resource, without opening the other project
files.

If you do not open the pool, you will only see assignment information
for the single project file you have opened.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"asuchi" <avitels.motels@gmail.com> wrote in message
news:AA7F741D-C63D-4468-986C-D153F78BF0F1@microsoft.com...
> Hi,
> when looking at the 'remaining work' of a resource which is assigned
> to
> more then one project, the number is different if all his projects are
> open
> or not.
> That is the way it should be? can't i know the remaining work of a
> resource
> unless i open all his projects?
>
> Thanks
>



Re: Remaining work in Resource usage view. by avitels

avitels
Mon Jun 04 01:11:00 CDT 2007

Hi Julie,
Thank you for the respond but i am using Project Server!
Do you have another idea?

Asuchi


"JulieS" wrote:

> Hello asuchi,
>
> An assumption:. You are working with a resource pool file which is
> providing resource to several project files. You are not using Project
> Server.
>
> When you open a project file, you should see a message asking if you
> want to "...open the resource pool file to see assignments across all
> sharer files."
>
> If you select the option to open the pool, you should see remaining work
> for all assignments for the resource, without opening the other project
> files.
>
> If you do not open the pool, you will only see assignment information
> for the single project file you have opened.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "asuchi" <avitels.motels@gmail.com> wrote in message
> news:AA7F741D-C63D-4468-986C-D153F78BF0F1@microsoft.com...
> > Hi,
> > when looking at the 'remaining work' of a resource which is assigned
> > to
> > more then one project, the number is different if all his projects are
> > open
> > or not.
> > That is the way it should be? can't i know the remaining work of a
> > resource
> > unless i open all his projects?
> >
> > Thanks
> >
>
>
>

Re: Remaining work in Resource usage view. by JulieS

JulieS
Mon Jun 04 09:30:20 CDT 2007

Hello Asuchi,

If you are using Project Server, please post your question to the
project server newsgroup (Microsoft.public.project.server). You may
also be able to find the answer by searching that newsgroup. You may
also find the answer on the Project Server experts website:

http://www.projectserverexperts.com/Shared%20Documents/Forms/AllItems.aspx

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"asuchi" <avitels.motels@gmail.com> wrote in message
news:3857428D-1FAE-425F-BE60-CB5EB72AC4E4@microsoft.com...
> Hi Julie,
> Thank you for the respond but i am using Project Server!
> Do you have another idea?
>
> Asuchi
>
>
> "JulieS" wrote:
>
>> Hello asuchi,
>>
>> An assumption:. You are working with a resource pool file which is
>> providing resource to several project files. You are not using
>> Project
>> Server.
>>
>> When you open a project file, you should see a message asking if you
>> want to "...open the resource pool file to see assignments across all
>> sharer files."
>>
>> If you select the option to open the pool, you should see remaining
>> work
>> for all assignments for the resource, without opening the other
>> project
>> files.
>>
>> If you do not open the pool, you will only see assignment information
>> for the single project file you have opened.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "asuchi" <avitels.motels@gmail.com> wrote in message
>> news:AA7F741D-C63D-4468-986C-D153F78BF0F1@microsoft.com...
>> > Hi,
>> > when looking at the 'remaining work' of a resource which is
>> > assigned
>> > to
>> > more then one project, the number is different if all his projects
>> > are
>> > open
>> > or not.
>> > That is the way it should be? can't i know the remaining work of a
>> > resource
>> > unless i open all his projects?
>> >
>> > Thanks
>> >
>>
>>
>>