Re: Recurring tasks by HelgeSvee
HelgeSvee
Mon Jan 16 02:14:05 CST 2006
It seems like it can't be done using "Recurring tasks" But I have found my
way around this "problem".
It most easy to use recurring task, but I found my solution but formatting
regular tasks. If I make 5 task and want No 1 to be Summary Task and No2 to
be "recurring task" and No 3 to 5 to be the sub tasks under the recurring. I
mark 3 to 5 and indent them under 2, and check the roll up to summary under
Task Information. For No 2 I indent it under No 1 and for both No 1 and No 2
I check the Show rolled up Gantt bars and Hide task bar in the Task
Information.
This is the solution.
JulieS skrev:
> Hi Helge,
>
> I have been playing with this off and on for the last few days since your
> original post. Try as I might, I cannot seem to find a way to make
> recurring task bars rollup to an upper level summary bar.
>
> Sorry, maybe someone else has discovered something I have overlooked.
>
> Julie
> "Helge Svee" <HelgeSvee@discussions.microsoft.com> wrote in message
> news:AB648F70-15C2-4BF0-96BA-18BF54597B61@microsoft.com...
> > Is it possible to roll up recurring tasks to summary
>
>
>