All - Looking for anyone with information regarding compatabilties between
2000 and 2003.

We have project files built using 2000. Multiple Project Managers (PM) apply
updates to the same project files. Some PM have been upgraded to XP w/ MSP
2003 and some are still on MSP 2000.

When a PM using MSP 2000 saves a project file after a PM using MSP 2003 has
saved it, a warning box appears stating saving the 2003 file back to 2000 may
lose some data.

Anyone know if any data actually will be lost or is it just a disclaimer?

Thanks!

Re: Project 2000 and 2003 users using same MPP by Jan

Jan
Fri Nov 18 16:22:01 CST 2005

Hi,

Only those data they may have added, that do not exist in 2000 (such as
multiple baselines) may be lost.
The original 2000 data will not be lost.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"toast88" <toast88@discussions.microsoft.com> schreef in bericht
news:332409C4-9D7E-4A31-A41A-3256DA030439@microsoft.com...
> All - Looking for anyone with information regarding compatabilties between
> 2000 and 2003.
>
> We have project files built using 2000. Multiple Project Managers (PM)
apply
> updates to the same project files. Some PM have been upgraded to XP w/ MSP
> 2003 and some are still on MSP 2000.
>
> When a PM using MSP 2000 saves a project file after a PM using MSP 2003
has
> saved it, a warning box appears stating saving the 2003 file back to 2000
may
> lose some data.
>
> Anyone know if any data actually will be lost or is it just a disclaimer?
>
> Thanks!