JulieS
Tue Oct 16 16:42:17 PDT 2007
You're welcome Michelle and thanks for the feedback.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"Michelle" <Michelle@discussions.microsoft.com> wrote in message
news:526EDC84-048B-4CAC-9767-1EC095EF7E9E@microsoft.com...
> thanks to all for your help on this - much appreciated!
>
> "JulieS" wrote:
>
>> Hello Michelle,
>>
>> In order to have an Actual Finish date which is earlier than the
>> scheduled finish date, you will need to fill in the Actual Finish
>> date.
>> If you simply mark a task 100% complete, Project will assume you
>> finished the task as originally scheduled. You may find using the
>> Tracking Table applied to either the Gantt chart or the Tracking
>> Gantt
>> Chart view helps.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit
http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "Michelle" <Michelle@discussions.microsoft.com> wrote in message
>> news:7D8F34DB-5629-411D-8C63-432D5E4A615B@microsoft.com...
>> > Hi dave, thanks for your reply. I think I have it sorted now, but I
>> > do
>> > have
>> > another question. I have set up a stoplight to monitor task &
>> > project
>> > schedules. This is all working OK and I have the relevant graphical
>> > indicators showing.
>> > I was testing getting a smilet face to show up when a task is
>> > completed
>> > earlier than the baseline finish date. I assumed this could be done
>> > just by
>> > setting the % complete to 100. This doesn;t seem to work though, i
>> > have to
>> > actually change the finish date on the task. Is that correct?
>> >
>> > "Dave" wrote:
>> >
>> >> Michelle wrote:
>> >> > I am trying to find out how I create a RAG status indicator for
>> >> > a
>> >> > project as
>> >> > opposed to a task. I have created a custom view in Project
>> >> > Centre,
>> >> > but I need
>> >> > to add one last column that shows the status of the project. Can
>> >> > someone
>> >> > help? I have seen info on indicators for tasks, but not for
>> >> > projects.
>> >> > thanks
>> >>
>> >>
>> >> First you need to determine what the criteria for for displaying
>> >> the
>> >> RAG
>> >> symbols. Can you tell us what they are and then we will probably
>> >> be
>> >> able to help more.
>> >>
>> >> Typically, these will be set depending on how far the Project
>> >> deviates
>> >> from baseline date and costs.
>> >>
>>
>>
>>