Change the task to type "Fixed Duration". Since you also want to specify the
work hours, the easiest way to do this (IMHO):
Window/Split
In the bottom pane, change task type to Fixed Duration, enter 4 days. In
the resource area of the form, add your resource and specify work as 12 hours.
Click OK.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"Rag742" wrote:
> I have tasks that has 4days duration. I know the resource of the
> project manager(PM) is 12 labor hours. Is there some way I can enter
> the PM labor hour as 12 . At present if i enter 12 hours it changes
> the duration and the resource unit also changes. I don't care about
> the resource unit all i want the 4days duration and 12 hours.