Hi,
I am using Project 98 to cost my resources that charge variable rates
depending on what time they work. Example, normal working day (9-5) is
charged at a normal rate, any time after that is overtime. The first 2
hours of overtime is charged at time and a half and any hours after
that (or weekends) is charged at double time. The problem of-course is
that Project only allows 1 Overtime field. Using an additional Cost
Table doesn't help because they are task specific. Any help please???
Caroline

Re: Project 98 - additional overtime fields by Rod

Rod
Fri Feb 17 01:20:05 CST 2006

The only compromise is to adjust the number of hours so the cost is correct,
but the hours wrong or add extra cost to the Fixed Cost field.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"CarolineB" <caroline@bainsworld.com> wrote in message
news:1140156146.170906.292810@f14g2000cwb.googlegroups.com...
> Hi,
> I am using Project 98 to cost my resources that charge variable rates
> depending on what time they work. Example, normal working day (9-5) is
> charged at a normal rate, any time after that is overtime. The first 2
> hours of overtime is charged at time and a half and any hours after
> that (or weekends) is charged at double time. The problem of-course is
> that Project only allows 1 Overtime field. Using an additional Cost
> Table doesn't help because they are task specific. Any help please???
> Caroline
>