Tue Oct 09 08:55:04 PDT 2007
Thanks for your responses Steve ... I think the best solution here is to use
what Jan suggested which is to use the 'Preleveled Start Date'.
Thanks all for your posts.
"Steve House" wrote:
> The "what changed at last calculation" feature of 2007 doesn't have any
> counterpart in 2003, sorry.
>
> --
> Steve House [Project MVP]
> MS Project Trainer & Consultant
> Visit
http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "newPM" <newPM@discussions.microsoft.com> wrote in message
> news:26BDBBDC-18AF-40E0-B9BC-792751F5F2EC@microsoft.com...
> > Hi Jan, Dale-
> >
> > Thanks for your prompt response. I like both of your suggestions and will
> > use them to understand how leveling has changed my dates ...
> >
> > However, I also really like how in Project 2007 the dates that are changed
> > are highlighted in blue to let me know which dates were changed when I run
> > 'Level Now' ... is there a way to see the impact of of the most recent
> > levelling run in 2003? From what I understand, the options that you listed
> > show the overall impact of leveling and not of the most recent run. Does
> > that
> > make sense? Is there a feature comparable to that in 2003.
> >
> >
> >
> > "Jan De Messemaeker" wrote:
> >
> >> Hi,
> >>
> >> On top of Dale's precious advice: I also use the Preleveled Start
> >> property
> >> (Insert, Column, Preleveled start)
> >> The difference is that when a task is postponed by leveling, and that
> >> moves
> >> its successor tasks, the successor tasks show 0 as leveling delay (their
> >> delay not DIRECTLY being caused by leveling)
> >> Preleveled start is available for comparison for all tasks regardless
> >> whether the move was induced directly by leveling or not.
> >> Attention: if you use Preleveled start it is better to explicitly perform
> >> Clear Leveling between two leveling exercices.
> >> Hope this helps,
> >>
> >> --
> >> Jan De Messemaeker
> >> Microsoft Project MVP
> >>
http://users.online.be/prom-ade
> >> "newPM" <newPM@discussions.microsoft.com> wrote in message
> >> news:D34740AF-1A2B-4864-A003-4F7254CD2048@microsoft.com...
> >> > Hello All-
> >> >
> >> > Do you know how to identify the dates that were updated in MS Project
> >> > 2003
> >> > after the leveling algorithm is run? In 2007 all updated dates will
> >> > show
> >> > up
> >> > in blue, but did not see that in Project 2003 ....
> >> >
> >> > TIA
> >> >
> >> > -f
> >>
> >>
> >>
>
>