Is it posisble to convert the Summary Duration from days into weeks or even
months?

Thanks

Re: Project Summary Duration by Mike

Mike
Thu Mar 13 17:01:03 CDT 2008

Hi Andrew,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Options.../Schedule tab and change Duration is entered in...

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials



"Andrew" <Andrew@discussions.microsoft.com> wrote in message
news:C256EE9E-97A1-4CE3-919F-F863390A911D@microsoft.com...
> Is it posisble to convert the Summary Duration from days into weeks or
> even
> months?
>
> Thanks



Re: Project Summary Duration by Andrew

Andrew
Thu Mar 13 18:08:00 CDT 2008

Mike

Wow so easy when you now how, thanks alot great help.

This is also a formating question, other than the standard fonts colors etc
are there any best pratice methods of displaying Gannt Charts, for example
should the Task Name be placed next to the barchart in Bar Text?

Thanks, Andrew

"Mike Glen" wrote:

> Hi Andrew,
>
> Welcome to this Microsoft Project newsgroup :)
>
> Try Tools/Options.../Schedule tab and change Duration is entered in...
>
> FAQs, companion products and other useful Project information can be seen at
> this web address: http://project.mvps.org/faqs.htm
>
> Hope this helps - please let us know how you get on :)
>
> Mike Glen
> MS Project MVP
> See http://tinyurl.com/2xbhc for Project Tutorials
>
>
>
> "Andrew" <Andrew@discussions.microsoft.com> wrote in message
> news:C256EE9E-97A1-4CE3-919F-F863390A911D@microsoft.com...
> > Is it posisble to convert the Summary Duration from days into weeks or
> > even
> > months?
> >
> > Thanks
>
>
>

Re: Project Summary Duration by sai

sai
Thu Mar 13 21:40:02 CDT 2008

Dear Andrew,

If you want to display the task name next to the task bar (also called as
gantt bar), then choose Format > Barstyle ..., and select the type of task
you want to customize. Select the Text tab and indicate the postion where the
task name be displayed. Field name of task name is Name.

Please let us know if this helps.

Regards
Sai [PMP]


"Andrew" wrote:

> Mike
>
> Wow so easy when you now how, thanks alot great help.
>
> This is also a formating question, other than the standard fonts colors etc
> are there any best pratice methods of displaying Gannt Charts, for example
> should the Task Name be placed next to the barchart in Bar Text?
>
> Thanks, Andrew
>
> "Mike Glen" wrote:
>
> > Hi Andrew,
> >
> > Welcome to this Microsoft Project newsgroup :)
> >
> > Try Tools/Options.../Schedule tab and change Duration is entered in...
> >
> > FAQs, companion products and other useful Project information can be seen at
> > this web address: http://project.mvps.org/faqs.htm
> >
> > Hope this helps - please let us know how you get on :)
> >
> > Mike Glen
> > MS Project MVP
> > See http://tinyurl.com/2xbhc for Project Tutorials
> >
> >
> >
> > "Andrew" <Andrew@discussions.microsoft.com> wrote in message
> > news:C256EE9E-97A1-4CE3-919F-F863390A911D@microsoft.com...
> > > Is it posisble to convert the Summary Duration from days into weeks or
> > > even
> > > months?
> > >
> > > Thanks
> >
> >
> >

Re: Project Summary Duration by Colin

Colin
Fri Mar 14 03:55:00 CDT 2008

Andrew

My personal preference is not to show the text. But if a customer required
it to be shown, i would just create a new view which would show this when
printing. I sometimes have numerous views available for different
departments, but always use the same view for my own updating.

Regards

Colin

"Andrew" wrote:

> Mike
>
> Wow so easy when you now how, thanks alot great help.
>
> This is also a formating question, other than the standard fonts colors etc
> are there any best pratice methods of displaying Gannt Charts, for example
> should the Task Name be placed next to the barchart in Bar Text?
>
> Thanks, Andrew
>
> "Mike Glen" wrote:
>
> > Hi Andrew,
> >
> > Welcome to this Microsoft Project newsgroup :)
> >
> > Try Tools/Options.../Schedule tab and change Duration is entered in...
> >
> > FAQs, companion products and other useful Project information can be seen at
> > this web address: http://project.mvps.org/faqs.htm
> >
> > Hope this helps - please let us know how you get on :)
> >
> > Mike Glen
> > MS Project MVP
> > See http://tinyurl.com/2xbhc for Project Tutorials
> >
> >
> >
> > "Andrew" <Andrew@discussions.microsoft.com> wrote in message
> > news:C256EE9E-97A1-4CE3-919F-F863390A911D@microsoft.com...
> > > Is it posisble to convert the Summary Duration from days into weeks or
> > > even
> > > months?
> > >
> > > Thanks
> >
> >
> >

Re: Project Summary Duration by Mike

Mike
Fri Mar 14 09:34:25 CDT 2008

You're welcome, Andrew :-)

There are no best practice methods - it's entirely up to you or your
customer. If you put the task name with the bar, you could do away with the
table on the left.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials


"Andrew" <Andrew@discussions.microsoft.com> wrote in message
news:D7AE6D74-9A0F-4021-B766-0699F8C18422@microsoft.com...
> Mike
>
> Wow so easy when you now how, thanks alot great help.
>
> This is also a formating question, other than the standard fonts colors
> etc
> are there any best pratice methods of displaying Gannt Charts, for example
> should the Task Name be placed next to the barchart in Bar Text?
>
> Thanks, Andrew
>
> "Mike Glen" wrote:
>
>> Hi Andrew,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> Try Tools/Options.../Schedule tab and change Duration is entered in...
>>
>> FAQs, companion products and other useful Project information can be seen
>> at
>> this web address: http://project.mvps.org/faqs.htm
>>
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>> See http://tinyurl.com/2xbhc for Project Tutorials
>>
>>
>>
>> "Andrew" <Andrew@discussions.microsoft.com> wrote in message
>> news:C256EE9E-97A1-4CE3-919F-F863390A911D@microsoft.com...
>> > Is it posisble to convert the Summary Duration from days into weeks or
>> > even
>> > months?
>> >
>> > Thanks
>>
>>
>>