Hello,

I am familiar with the MS advice on Hammock Tasks (141733 et al.) and have
used them on a number of occasions to great effect in Project'98 and '2000.

I am having difficulties in getting them to work correctly for a Client in
Project'2002. Is there any advice or experience on this? Does v.2002-on
handle these differently? I can find no new advice in the system concerning
the later versions and would be grateful for an update.

Many thanks,
Jim Trickett

Re: MS Project 2002 - Hammock Tasks by JackD

JackD
Thu Nov 18 11:03:14 CST 2004

Should work just the same.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Jim Trickett" <Jim Trickett@discussions.microsoft.com> wrote in message
news:D5D907EE-51EC-4233-B320-BD23D5C42EF5@microsoft.com...
> Hello,
>
> I am familiar with the MS advice on Hammock Tasks (141733 et al.) and have
> used them on a number of occasions to great effect in Project'98 and
'2000.
>
> I am having difficulties in getting them to work correctly for a Client in
> Project'2002. Is there any advice or experience on this? Does v.2002-on
> handle these differently? I can find no new advice in the system
concerning
> the later versions and would be grateful for an update.
>
> Many thanks,
> Jim Trickett



RE: MS Project 2002 - Hammock Tasks by JimTrickett

JimTrickett
Fri Nov 19 04:41:04 CST 2004

Thanks Jack, I had hoped there were no changes in that respect. However, the
problem I am having is that, on following procedures to put the Hammock Task
in place, its Duration remains as '1d?' and it does not fill the gap as it
should.

The 1d? Task just zips to one end or the other, depending upon which Link
was input first.

I have set up a dummy programme and the thing works perfectly, but the
Client's programme is being a pain in this respect.

Any ideas?
Jim Trickett

"Jim Trickett" wrote:

> Hello,
>
> I am familiar with the MS advice on Hammock Tasks (141733 et al.) and have
> used them on a number of occasions to great effect in Project'98 and '2000.
>
> I am having difficulties in getting them to work correctly for a Client in
> Project'2002. Is there any advice or experience on this? Does v.2002-on
> handle these differently? I can find no new advice in the system concerning
> the later versions and would be grateful for an update.
>
> Many thanks,
> Jim Trickett

Re: MS Project 2002 - Hammock Tasks by JulieD

JulieD
Fri Nov 19 08:03:04 CST 2004

Hi Jim

it works when i test it under any conceivable situation i throw at it ... so
have you tried the good old "delete the task, close project, open project &
try again" method of trouble shooting :)

anything else 'odd' about the client's sitatuation (ie no service packs,
scheduling from a finish date - not that this seemed to make a difference
when i tested it).

Cheers
JulieD



"Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
news:936708BF-51B7-499A-A8D3-A8FB05618BF9@microsoft.com...
> Thanks Jack, I had hoped there were no changes in that respect. However,
> the
> problem I am having is that, on following procedures to put the Hammock
> Task
> in place, its Duration remains as '1d?' and it does not fill the gap as it
> should.
>
> The 1d? Task just zips to one end or the other, depending upon which Link
> was input first.
>
> I have set up a dummy programme and the thing works perfectly, but the
> Client's programme is being a pain in this respect.
>
> Any ideas?
> Jim Trickett
>
> "Jim Trickett" wrote:
>
>> Hello,
>>
>> I am familiar with the MS advice on Hammock Tasks (141733 et al.) and
>> have
>> used them on a number of occasions to great effect in Project'98 and
>> '2000.
>>
>> I am having difficulties in getting them to work correctly for a Client
>> in
>> Project'2002. Is there any advice or experience on this? Does v.2002-on
>> handle these differently? I can find no new advice in the system
>> concerning
>> the later versions and would be grateful for an update.
>>
>> Many thanks,
>> Jim Trickett



Re: MS Project 2002 - Hammock Tasks by JackD

JackD
Fri Nov 19 11:24:37 CST 2004

I don't use hammock tasks much, so I'm not sure if it has an effect, but
perhaps try changing the task type (fixed duration, fixed work, fixed units)
to something different from what it is.

What exactly is the process you are following?

You should be selecting and copying the date from one cell and then pasting
"text data"- making sure that that the "paste link" option is selected. If
you forget to check the paste link then of course it will not work and you
get the behavior that you have described.

It MUST be a link.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
news:936708BF-51B7-499A-A8D3-A8FB05618BF9@microsoft.com...
> Thanks Jack, I had hoped there were no changes in that respect. However,
the
> problem I am having is that, on following procedures to put the Hammock
Task
> in place, its Duration remains as '1d?' and it does not fill the gap as it
> should.
>
> The 1d? Task just zips to one end or the other, depending upon which Link
> was input first.
>
> I have set up a dummy programme and the thing works perfectly, but the
> Client's programme is being a pain in this respect.
>
> Any ideas?
> Jim Trickett
>
> "Jim Trickett" wrote:
>
> > Hello,
> >
> > I am familiar with the MS advice on Hammock Tasks (141733 et al.) and
have
> > used them on a number of occasions to great effect in Project'98 and
'2000.
> >
> > I am having difficulties in getting them to work correctly for a Client
in
> > Project'2002. Is there any advice or experience on this? Does v.2002-on
> > handle these differently? I can find no new advice in the system
concerning
> > the later versions and would be grateful for an update.
> >
> > Many thanks,
> > Jim Trickett



Re: MS Project 2002 - Hammock Tasks by JimTrickett

JimTrickett
Mon Nov 29 07:13:12 CST 2004

Hello Jack,
Thanks for the advice.
the problem was in one particular file and a predessessor had set Task Types
to Fixed Duration (Hammocks don't appear to work in Fixed Duration - might be
worth passing on(?) Nor can you change the Task Type to make it work, it MUST
be on a 'virgin' task so delete and re-type is the only answer)

Thanks again,
Jim Trickett

"JackD" wrote:

> I don't use hammock tasks much, so I'm not sure if it has an effect, but
> perhaps try changing the task type (fixed duration, fixed work, fixed units)
> to something different from what it is.
>
> What exactly is the process you are following?
>
> You should be selecting and copying the date from one cell and then pasting
> "text data"- making sure that that the "paste link" option is selected. If
> you forget to check the paste link then of course it will not work and you
> get the behavior that you have described.
>
> It MUST be a link.
>
> --
> -Jack ... For project information and macro examples visit
> http://masamiki.com/project
>
> ..
> "Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
> news:936708BF-51B7-499A-A8D3-A8FB05618BF9@microsoft.com...
> > Thanks Jack, I had hoped there were no changes in that respect. However,
> the
> > problem I am having is that, on following procedures to put the Hammock
> Task
> > in place, its Duration remains as '1d?' and it does not fill the gap as it
> > should.
> >
> > The 1d? Task just zips to one end or the other, depending upon which Link
> > was input first.
> >
> > I have set up a dummy programme and the thing works perfectly, but the
> > Client's programme is being a pain in this respect.
> >
> > Any ideas?
> > Jim Trickett
> >
> > "Jim Trickett" wrote:
> >
> > > Hello,
> > >
> > > I am familiar with the MS advice on Hammock Tasks (141733 et al.) and
> have
> > > used them on a number of occasions to great effect in Project'98 and
> '2000.
> > >
> > > I am having difficulties in getting them to work correctly for a Client
> in
> > > Project'2002. Is there any advice or experience on this? Does v.2002-on
> > > handle these differently? I can find no new advice in the system
> concerning
> > > the later versions and would be grateful for an update.
> > >
> > > Many thanks,
> > > Jim Trickett
>
>
>

Re: MS Project 2002 - Hammock Tasks by JackD

JackD
Mon Nov 29 11:43:06 CST 2004

Glad it worked out, and thanks for posting back what worked. I'm sure it
will help someone else who has the same problem in the future.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
news:717BBF88-B5FE-4501-B941-7E7B3F18104B@microsoft.com...
> Hello Jack,
> Thanks for the advice.
> the problem was in one particular file and a predessessor had set Task
Types
> to Fixed Duration (Hammocks don't appear to work in Fixed Duration - might
be
> worth passing on(?) Nor can you change the Task Type to make it work, it
MUST
> be on a 'virgin' task so delete and re-type is the only answer)
>
> Thanks again,
> Jim Trickett
>
> "JackD" wrote:
>
> > I don't use hammock tasks much, so I'm not sure if it has an effect, but
> > perhaps try changing the task type (fixed duration, fixed work, fixed
units)
> > to something different from what it is.
> >
> > What exactly is the process you are following?
> >
> > You should be selecting and copying the date from one cell and then
pasting
> > "text data"- making sure that that the "paste link" option is selected.
If
> > you forget to check the paste link then of course it will not work and
you
> > get the behavior that you have described.
> >
> > It MUST be a link.
> >
> > --
> > -Jack ... For project information and macro examples visit
> > http://masamiki.com/project
> >
> > ..
> > "Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
> > news:936708BF-51B7-499A-A8D3-A8FB05618BF9@microsoft.com...
> > > Thanks Jack, I had hoped there were no changes in that respect.
However,
> > the
> > > problem I am having is that, on following procedures to put the
Hammock
> > Task
> > > in place, its Duration remains as '1d?' and it does not fill the gap
as it
> > > should.
> > >
> > > The 1d? Task just zips to one end or the other, depending upon which
Link
> > > was input first.
> > >
> > > I have set up a dummy programme and the thing works perfectly, but the
> > > Client's programme is being a pain in this respect.
> > >
> > > Any ideas?
> > > Jim Trickett
> > >
> > > "Jim Trickett" wrote:
> > >
> > > > Hello,
> > > >
> > > > I am familiar with the MS advice on Hammock Tasks (141733 et al.)
and
> > have
> > > > used them on a number of occasions to great effect in Project'98 and
> > '2000.
> > > >
> > > > I am having difficulties in getting them to work correctly for a
Client
> > in
> > > > Project'2002. Is there any advice or experience on this? Does
v.2002-on
> > > > handle these differently? I can find no new advice in the system
> > concerning
> > > > the later versions and would be grateful for an update.
> > > >
> > > > Many thanks,
> > > > Jim Trickett
> >
> >
> >



Re: MS Project 2002 - Hammock Tasks by Sue

Sue
Wed Nov 02 15:57:02 CST 2005

Thank you so very much! It's hard to believe that it doesn't say somewhere
in the documentation that "the hammock task cannot be type 'fixed duration'
".

-Sue

"JackD" wrote:

> Glad it worked out, and thanks for posting back what worked. I'm sure it
> will help someone else who has the same problem in the future.
>
> --
> -Jack ... For project information and macro examples visit
> http://masamiki.com/project
>
> ..
> "Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
> news:717BBF88-B5FE-4501-B941-7E7B3F18104B@microsoft.com...
> > Hello Jack,
> > Thanks for the advice.
> > the problem was in one particular file and a predessessor had set Task
> Types
> > to Fixed Duration (Hammocks don't appear to work in Fixed Duration - might
> be
> > worth passing on(?) Nor can you change the Task Type to make it work, it
> MUST
> > be on a 'virgin' task so delete and re-type is the only answer)
> >
> > Thanks again,
> > Jim Trickett
> >
> > "JackD" wrote:
> >
> > > I don't use hammock tasks much, so I'm not sure if it has an effect, but
> > > perhaps try changing the task type (fixed duration, fixed work, fixed
> units)
> > > to something different from what it is.
> > >
> > > What exactly is the process you are following?
> > >
> > > You should be selecting and copying the date from one cell and then
> pasting
> > > "text data"- making sure that that the "paste link" option is selected.
> If
> > > you forget to check the paste link then of course it will not work and
> you
> > > get the behavior that you have described.
> > >
> > > It MUST be a link.
> > >
> > > --
> > > -Jack ... For project information and macro examples visit
> > > http://masamiki.com/project
> > >
> > > ..
> > > "Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
> > > news:936708BF-51B7-499A-A8D3-A8FB05618BF9@microsoft.com...
> > > > Thanks Jack, I had hoped there were no changes in that respect.
> However,
> > > the
> > > > problem I am having is that, on following procedures to put the
> Hammock
> > > Task
> > > > in place, its Duration remains as '1d?' and it does not fill the gap
> as it
> > > > should.
> > > >
> > > > The 1d? Task just zips to one end or the other, depending upon which
> Link
> > > > was input first.
> > > >
> > > > I have set up a dummy programme and the thing works perfectly, but the
> > > > Client's programme is being a pain in this respect.
> > > >
> > > > Any ideas?
> > > > Jim Trickett
> > > >
> > > > "Jim Trickett" wrote:
> > > >
> > > > > Hello,
> > > > >
> > > > > I am familiar with the MS advice on Hammock Tasks (141733 et al.)
> and
> > > have
> > > > > used them on a number of occasions to great effect in Project'98 and
> > > '2000.
> > > > >
> > > > > I am having difficulties in getting them to work correctly for a
> Client
> > > in
> > > > > Project'2002. Is there any advice or experience on this? Does
> v.2002-on
> > > > > handle these differently? I can find no new advice in the system
> > > concerning
> > > > > the later versions and would be grateful for an update.
> > > > >
> > > > > Many thanks,
> > > > > Jim Trickett
> > >
> > >
> > >
>
>
>