Start 7/15/07, Finish 8/3/07 - This is 20 days.
Why does Duration show "18.21 days?"
There is actually a "?" after the word "days".

I would like to have Saturdays and Sundays as a working day. Also, want the
work day to be 24 hours vice 8 hours.

I need the top example to produce a Duration of 20 days.

How can I make this happen.
Thanks for any help - new to Project
Pete

Re: Project Duration Days Incorrect by Jan

Jan
Fri Feb 17 13:21:29 CST 2006

Hi Pete,

Quite a lot of questions, here are some answer.
Don't worry about the "?"; it'll only be there till you enter a duration, it
shows the original default 1 day is there. It doe NOT influence any
calculation.

As for the 18,21 days: it's a long story and it is best explained in

http://www;mvps.org/faqs.htm
faq 5. Default Working hours

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Pete Sperling" <PeteSperling@discussions.microsoft.com> schreef in bericht
news:E1F68B3B-E7E2-4958-97F6-A2B8628D44DC@microsoft.com...
> Start 7/15/07, Finish 8/3/07 - This is 20 days.
> Why does Duration show "18.21 days?"
> There is actually a "?" after the word "days".
>
> I would like to have Saturdays and Sundays as a working day. Also, want
the
> work day to be 24 hours vice 8 hours.
>
> I need the top example to produce a Duration of 20 days.
>
> How can I make this happen.
> Thanks for any help - new to Project
> Pete