Project viewer?
Microsoft has a Powerpoint viewer so it is not necessary to install the full
version of Powerpoint to view a PPT.
Is there anything equivalent for Project? (Either Microsoft or third party)
Thanks,
Steve Tag: Priority Tag: 62319
Actual work
Hi
Is it possible to restrict the resource from booking the actual work more than the estimated hour.
For ex. if a task has bee allocated 10 hrs.. is it possible to restrict the resource from booking more than 10 hours?. I want the resource to get the extra hours allocated from the project manager in case he requires more time.
Can any one suggest regarding this
Cheer
arun. Tag: Priority Tag: 62317
Importing Project schedules into Word.
Hi,
Is there a simple way of selecting a MS Project and importing it into a Word
Document, a lot of our reports also need to have programme information with
them but the current method is to do a screengrab and import the image into
an A3 sheet as a bitmap. The results are somewhat less than professional but
Project/Word do not seem to collaborate using OLE. Is there a decent work
around?
Regards
Jonathan Tag: Priority Tag: 62311
Custom Reports
Hi,
I need to generate a report from Project 2002, which provides the following
information,
Resource Name (from a resource pool not a schedule).
Project Name, Task, Start Date, Finish Date, % Complete, Actual Start,
Actual Finish
Which is sorted against the Start and Finish Dates. The idea is to be able
to print out for any given employee, a list of ongoing tasks within a given
week period. The report needs to contain ongoing tasks as well as those that
start during the given period.
The program planner has had limited success in defining this report so
hopefully someone out there might be able to give me a walkthrough.
Regards
Jonathan
<mailto: haigh@remove_this_text.cae.com> Tag: Priority Tag: 62310
Old Project File
hi. i have an old project file, that i can't open with
microsoft project 2000, does anyone know, what version of
project i may need to open a file that was created in
94/95.
thanks
ag Tag: Priority Tag: 62306
Tasks "on hold"
Waht is the best way to indicate that a task is "on-
hold." Often customer's need to obtain approval,
additional funding etc such that a task does not get
completed as planned. When this happens I don't want to
loose the task, but want to follow it as a reminder.
/ray Tag: Priority Tag: 62303
Identify current tasks?
Is there a simple way of highlighting current (on-going) tasks in the task
list?
I'd like to see (in the Gantt chart view) the tasks that are presently being
worked on.
Cheers.
Bobby Tag: Priority Tag: 62298
Error Saving Project: "[Microsoft][ODBC SQL Server Driver]Communication link failure"
- I open up Project Professional 2003. I clearly see that it
automatically logs me into Project Server 2003.
- I press the "save" toolbar button
- I give the project a name and press "save". No problem.
- I add tasks, named "1" "2" "3" "4" "5" (I do not type in any of the
other columns)
- I press the "save" toolbar button. No problem.
- I continue adding tasks, named "6" "7" "8" "9" "10". I press the
"save" toolbar button. No problem.
- I continue adding tasks, named "11" thru "21". I press the "save"
toolbar button. No problem.
- I add a task named "22." I press the "save" toolbar button. ERROR:
"[Microsoft][ODBC SQL Server Driver]Communication link failure"
- I press "save" again. ERROR:
" [Microsoft][ODBC SWL Server Driver][SQL Server]Cannot insert
duplicate key row into object 'MSP_TASKS' with unique index
'I_MSP_TASKS'. "
This happens CONSISTENTLY. I can reproduce this over and over again.
Please help! This is stopping me from deploying and using Project
Server companywide.
Thanks,
Mike Tag: Priority Tag: 62297
Leveled project - resources still overallocated
I have a project that showed overallocations for several
of my resources. I selected all tasks, went to
Project/Task Information/Advanced and selected "As Soon As
Possible" for the Constraint Type. I then leveled
resources and several tasks were affected. In addition,
my Finish date was pushed out by several weeks. However,
when I go back to look at my Resource Graph, although it
looks better I still see overallocations. Is there a way
to level so that all overallocations are removed? Tag: Priority Tag: 62296
Changing Colors of Task Names
Does anyone know a way to change the color of the task
name based on a test of a flag field?
As an example if the flag field had either 1,2 or 3
assigned to it....Is there a way to print 1's in red, 2's
in blue etc.? I realize the bar on the gantt can be
changed but I would like to change the color of the task
name to further highlight tasks that are critical in
nature. Tag: Priority Tag: 62295
Modify start dates of all tasks...
Is it possible to modify the start date of all tasks
instead of changing each one individually? Example, my
project was delayed by one week and I would like to
adjust the start of each task by + 1 week. Anyone know
how to accomplish this? Tag: Priority Tag: 62294
MS Project 2003 & EPM presentation
Hi all
I'm looking for a presentation (powerpoint format) of MS Project 2003 and/or EPM (Enterprise Project Management), features and benefits. I was not able to find that on Microsoft web site.
Thanks in advanc
Jean-Paul Tag: Priority Tag: 62293
Print showing outline symbols
Whenever I print the outline symbols don't show up but
they do on the screen. Is there someway I can make the
symbols print to.
Thanks,
Rachael Tag: Priority Tag: 62285
compatible question
Does anyboby know that whether Project2003 standard
version can read the files created by Project2003
professional version?
Thanks a lot! Tag: Priority Tag: 62281
Macros are not visible from the other machine
I have created 'macros' and saved them globally with the
MS project (on NetWork drive).When my colleague opened the
same from her machine, the macros were not getting
displayed. The Macros I have created were been saved
globally. I have checked the security settings on MS
project. The Security level is Medium on both MS project
views.
Does any one know what could be happening? Any hint on
this would be highly appreciated Tag: Priority Tag: 62264
Link Line Colors
OK, I can't find any way of changing the color of the link lines without changing the color of the bars that they connect to - is this something that is not available in Project? Seems like a rather simple function to implement ..... Tag: Priority Tag: 62262
Passwording Flagged Tasks
I need to hide some Flag1 tasks which are proprietary and very sensitive in nature. No problem. The situation is I don't want anyone else who has access to this schedule to be able unhide and view these flagged tasks. Is there a way to password these by a subroutine that will run automatically when the project is opened
Thanks................TomCat Tag: Priority Tag: 62254
Can I have Fixed "work" after recording actuals
I have a resource that I have split between three
different task items that run at the same time. For
planning purposes I allocated the task as follows.
Task A: 50%
Task B: 35%
Task C: 15%.
Lets assume this is one resource and all three tasks have
a duration of 2 weeks. So the allocations are
4 hours for task A
2.8 hours for task B
1.2 hours for task C.
This is the planned allocation of work for this resource.
When I get the actual hours for day 1, 2 and 3. Lets
assume the resource puts in
5 hours for task A
2.8 hours for task B
.2 hours for task C
for all three days.
Is there any way to keep task C (only) from not changing
the "planned" hours of work for the rest of the duration?
I ask this because task C is really a "Support Role"
task. The task does not have a set number of hours, I am
just reserving 1.2 hours for support functions, I only
want to allocate the 1.2 hours a day, regardless of how
much was used the previous day. For task A and B, I want
it to account for what has already been done, so I am okay
with how that works. It's just task C I want to have
fixed "work" no matter what the actual work done was. Is
there any way to do this? Tag: Priority Tag: 62251
Need immediate reply...Thanx a lot!
When i try to run Customize project Guide in MS Project
Proffesional 2003, it gives the folowing message box
"An ActiveX control on this page might be unsafe..."
I want to bypass the message box and set its status
from "Prompt" to "Enabled".
What should i do? as if i go to security of
internet/interanat but i dont know the exact place where
i have to set it .
Thanks and waiting for your replies.
-Rasheed Tag: Priority Tag: 62250
is the duration adjusted based on actual start/finish dates
If my actual start and finish dates are different then my baseline does the duration automatically adjust to reflect the change or is that just visible by look at the tracking gnatt and noting the delta
Thanks Tag: Priority Tag: 62249
How to view assignments that are slipping
Good Morning:
Is there a way to show all assignments that are past the
finish date. For example, if Task1 is 80% complete and
the finish date is less than today's date how can I get
these tasks to show in a different color. Can this be
done automatically in MSProject 2000 or do I need to write
a Macro. If a macro is needed does anyone have an example?
Any help would be very much appreciated.
Thank you. Tag: Priority Tag: 62241
general schedule tracking question
I have set a baseline for my project and have been tracking progress. I have had tasks that have slipped so there ar
new start and finish dates which have been adjusted by project. Project automatically makes the "actual start" and
"actual finish" equal to the start and finish dates. This is really confusing because it looks like tasks may be completing.
Is there a way to control this so the actual start and finish are empty or "NA" until I actually go in and update them.
I know project will assume the task has started if the start date has passed is there a way to control this or at least control the finish date to not be set until I enter the date
Thanks Tag: Priority Tag: 62237
Compare function in Project 2002
I'm running MS Project 2002 and downloaded the Compare two projects add-in from MS. It doesn't work at all, when I try to use it, nothing happens
Any ideas? Anyone have any opinions on this add-in in general
Thanks! Tag: Priority Tag: 62235
Linking hours into Excel, without the 'h'
Hi
I link data from my project plan into excel to do some
resource demand forcasting, or rather I'd like to, but
when I copy the hours against a task into my Excel sheet,
it includes the 'h' against the number to signify hours.
I need to get rid of this, as it wont allow the formulae
to carry out any number crunching on that cell with a
letter in it.
Any ideas? Do I need to put a custom field into project
that just shows the number of hours without the 'h'? If
so - how?!?!
TIA
Tim Tag: Priority Tag: 62229
export Start/Finish Time (not Date)
How can I export (e.g. to excel) the start/finish TIMES that MS project calculates automatically (based on dependencies, the calendar settings etc). I know how to export the start/finish dates : choosing the "microsoft project field" called "start" and "finish", but there is no such field for the start/finish times (e.g. at what time during the day is a task planned to start and stop). Is it possible to get those times exported, next to the dates ? Tag: Priority Tag: 62227
emails
Hiya
Project & PWA 2003
Are there more global ways of emailing task notifications than just the
person that receives the task that sets up his notifications ? eg. can
someone else be notified if a new task is created or a certain task reaches
completion.
regards
Martin Tag: Priority Tag: 62224
Actual Work / Work / Baseline Work
Hi All
'Actual work' is work actually performed and "Work" is the total work that
was/is scheduled. If the project baseline is saved at the start of the
project, the 'work baseline' equals the scheduled 'work'.
I have been trying out scenarios and noted when the 'actual work' is greater
than the baseline (and the baseline is equal to the 'work') the 'work' is
adjusted to the same total as 'actual work'. Is this correct?
If so, how do I show the extra hours of 'actual work' performed over and
above the baseline? Surely this would impact on my earned value, I am
assuming earned value is calculated from baseline figures, and any variance
of 'actual work' / work is reported against the baseline.
Can someone please provide some guidance?
TIA to all whom respond - Vers Tag: Priority Tag: 62211
Resource Managers
What is the best process in microsoft project to assign resources, utilizing a resource manager? I mean project managers can always assign resources to their projects but in this environment the resource managers want the control and tell pms who is available and not. How do they communicate and what if priority changes
Than
John Tag: Priority Tag: 62210
Default dates for Request Progress Information
I am trying to use the Email Updates in MSP Pro 2002, as
we don't have Server set up yet.
On the Request Progress Info page the default period seems
to be consistently way out from the current dates.
Anyone know how to change this automatically or change the
default? It is a pain to do it manually every time.
Thanks! Tag: Priority Tag: 62205
Error: Publish New and Changed Assignments
Project Pro 2002
Collaborate -> Publish -> New and Changed Assignments
Sends email to the resource
Resource hits Reply and then Send
Gets: An error occurred during initialization. An error
occurred while saving the file. The data was not saved.
You have to hit OK and it goes awya with nothing
happening.
Any ideas? Tag: Priority Tag: 62203
Filtering Tasks
I was just curious if there was a way to filter based
solely on the Task ID number, so that I could pick
arbitrary tasks throughout the project to show to
someone. I would appreciate any insight you might have.
Thanks,
Rachael Tag: Priority Tag: 62201
Can we arrange the sequence of tasks instead of inputting the start-end time.
Can we arrange the sequence of tasks instead of inputting the start-end time?
Our project is just a Nation Science Foundation project. So we can not know the end time of each task. but we know the sequence of each task. Can we arrange the sequence of tasks instead of inputting the start-end time?
Thanks! Tag: Priority Tag: 62185
What is use of SQLServer in MS Project Server Collaboration Environment
What is use of SQLServer in MS Project Server Collaboration Environment? Is there any limitation in the size of the files that project team members upload for each task because we only have MS Project Server2003 + Project 2003+ SQLServer 2000(Standard version)? I am not sure whether the size of SQLServer 2000(Standard version) decides the size of the files that project team members upload for each task. I heard that the size of SQLServer 2000 (Standard version) is only 2GB? Tag: Priority Tag: 62184
How can I freeze allocation %?
I posted a similar question before, but I still haven't
solved this maddening problem. Frequently when I update my
plan from project server the % allocation units change on
their own. So even though I have painstakingly set up
allocations showing how an individual should split his
time, after the update, these allocations change. Isn't
there some way to freeze the values I enter?
None of my tasks are effort driven and they are all set to
fixed units.
quickly loosing it...
Ben Tag: Priority Tag: 62183
Problem displaying Images/Pictures: Red "X" in IE
I have a computer that is acting strange, it is
displaying "Submit Status Report" improperly. Three
Red "X" are placed where the edit window boxes are.
Therefore the user cannot write or edit Status Report.
But every where else are working fine. I did the Q283807
and no luck at all.
The step 1, I looked at the properties and the "Type" is
showing "Unknown"
The system does not have any firewall/proxy installed.
One step I did not understand, the step 3 mentions Toggle
Images.exe on the "Link" toolbar. I couldn't find it.
The computer has Windows XP SP1 + IE 6 SP1 and all the
Windows Updates installed. There is nothing to update.
I have also tried to login as different user, same problem.
Any idea/links/solutions are welcome. Thanks all.
Johnny Tag: Priority Tag: 62182
Microsoft Project 98
I am having trouble printing on 8 1/2 by 14 paper. My
project is only coming out on 8 1/2 by 11. How can I
adjust this to print out? Tag: Priority Tag: 62180
Creating a custom Report
I am trying to create a report that shows a specific milestone for multiple projects. In other words - my schedule file is comprised of multiple small projects. However, there are several milestones that are common to all of the projects. What I want is to able to create a report that shows when each milestone (Ex. PDR) is going to occur. The only columns I am interested in having is the Task Name column, start & finish. This seems like it should be easy, but I am getting a lot of columns that I do not want. Also, I do have a filter so that my Gantt view will only display these milestones
Thanks in advance
Bill Tag: Priority Tag: 62176
Using e-mail to notify resources of assigned tasks
I don't have MS Project Server, nor can I post my project to the internet. I want to inform my resources (personnel) of assigned tasks via e-mail. I've successfully sent the e-mails, but they appear as .mtm attachments in Outlook. Is there a way to send the assignments so the recipient can show it as a task (and then be able to update % complete, etc.)? How do I do this? Tag: Priority Tag: 62168
Timeline Desire to show only 5 days, not 7
I am running a project during the week only, requiring no
weekends. How do i take saturday and sunday off of the
chart. Tag: Priority Tag: 62158
How not to show % assignment units
Hi All:
I don't want the % assignment units to show on my Gantt
Chart and I don't know how to do this.
Any help would be very much appreciated.
Thank you. Tag: Priority Tag: 62156
How not to show % assignment units
Hi All:
I don't want the % assignment units to show on my Gantt
Chart and I don't know how to do this.
Any help would be very much appreciated.
Thank you. Tag: Priority Tag: 62155
# jobs per task
In Project Server, is there a maximum number of jobs you can assign per task in a project
Thanks for any help
Jessica Tag: Priority Tag: 62146
project 2003 on Win98?
I have a really old machine that's running Win 98 - I'd
prefer to not upgrade the OS, but I'd like to buy MS
Project, the current version of which appears to only
support Win2K or XP. Does anyone know if it's possible to
install and run Project 2003 on a Win98 machine? Tag: Priority Tag: 62142
Problems installing Project 2003
Purchased copy of project 2003. Insert CD, install
begins. Error message "Error opening installation log
file. Verify that the specified log file location exists
and is writable". Have no idea what that means. I
haven't specified anything - it's on autorun and works
fine on another machine. Online help beyond useless -
apparently, on the drop down list, I've bought something
that does't exist, and unless you can click on product
names and enter product numbers - none of which it
allowed me to do as I couldn't identify it - you end up
in a somewhat circular and very frustrating loop.
Any suggestions? Tag: Priority Tag: 62134
Overallocation problem
Hello,
I am entering tasksthen assign them to an individual. Forexample when the
start dates of tasks are same. Ms project occupies same hour for two tasks.
It puts 2 hour work for example 11:00 a.m. I do not understand how to solve
it. Please help.
Burcu Tag: Priority Tag: 62131
Hello!
Can somebody please explain what is the priority field in
the Project Information window? What is its purpose?
Thanks in advance,
Mari