Mike
Mon Nov 21 03:41:20 CST 2005
Hi Schalk ,
Welcome to this Microsoft Project newsgroup :)
Try Tools/Options.../Calculation tab and set calculation to Automatic.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
Schalk wrote:
> I have two subtasks that starts on 07/11/05 if i put a predessesor
> on the second task it should update the start and end dates but it
> just stays the same,please help.
> ms project 2003