Hello,

For a specific resource I try to change the status of a weekend to
"Nondefault working time".
Although in the "Resource Information" dialog everything seems ok, I still
can not assign a task to that resource for weekends.
I use the same calendar both for the task and the resource.

Can anybody help?

Thanks,

AHMET

Re: Why "Nondefault working time" does not work? by John

John
Tue Jul 04 10:09:41 CDT 2006

In article <OHh1lfznGHA.3320@TK2MSFTNGP04.phx.gbl>,
"Ahmet Gunes" <gunesahm@hotmail.com> wrote:

> Hello,
>
> For a specific resource I try to change the status of a weekend to
> "Nondefault working time".
> Although in the "Resource Information" dialog everything seems ok, I still
> can not assign a task to that resource for weekends.
> I use the same calendar both for the task and the resource.
>
> Can anybody help?
>
> Thanks,
>
> AHMET

AHNET,
Your post says you "tried" to make the weekends as working time for that
specific resource. Well, is it or is it not? Does the Working Time tab
of the Resource Information dialogue for that resource show weekends as
"nondefault working time"?

Did you assign that resource to a task that bridges a weekend? What
makes you think that resource is not assigned for weekend work on
his/her tasks (look at the Resource Usage view)?

John
Project MVP

Re: Why "Nondefault working time" does not work? by Ahmet

Ahmet
Tue Jul 04 11:03:57 CDT 2006

Hello John,

In the Resource Information dialog everything seems ok. That's the weekend
is marked as nondefault working time.
When I try to assign a task to a resource for this weekend I get the message
"You moved 'Task xxx' to a nonworking day".

Thanks,

AG



"John" <mjensen@theriver.com> wrote in message
news:mjensen-755316.08094104072006@msnews.microsoft.com...
> In article <OHh1lfznGHA.3320@TK2MSFTNGP04.phx.gbl>,
> "Ahmet Gunes" <gunesahm@hotmail.com> wrote:
>
> > Hello,
> >
> > For a specific resource I try to change the status of a weekend to
> > "Nondefault working time".
> > Although in the "Resource Information" dialog everything seems ok, I
still
> > can not assign a task to that resource for weekends.
> > I use the same calendar both for the task and the resource.
> >
> > Can anybody help?
> >
> > Thanks,
> >
> > AHMET
>
> AHNET,
> Your post says you "tried" to make the weekends as working time for that
> specific resource. Well, is it or is it not? Does the Working Time tab
> of the Resource Information dialogue for that resource show weekends as
> "nondefault working time"?
>
> Did you assign that resource to a task that bridges a weekend? What
> makes you think that resource is not assigned for weekend work on
> his/her tasks (look at the Resource Usage view)?
>
> John
> Project MVP





Re: Why "Nondefault working time" does not work? by Steve

Steve
Tue Jul 04 11:36:14 CDT 2006

Did you actually define working hours on those days?

--
Steve House
MS Project MVP
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"Ahmet Gunes" <gunesahm@hotmail.com> wrote in message
news:eAdNnR4nGHA.3348@TK2MSFTNGP03.phx.gbl...
> Hello John,
>
> In the Resource Information dialog everything seems ok. That's the
weekend
> is marked as nondefault working time.
> When I try to assign a task to a resource for this weekend I get the
message
> "You moved 'Task xxx' to a nonworking day".
>
> Thanks,
>
> AG
>
>
>
> "John" <mjensen@theriver.com> wrote in message
> news:mjensen-755316.08094104072006@msnews.microsoft.com...
> > In article <OHh1lfznGHA.3320@TK2MSFTNGP04.phx.gbl>,
> > "Ahmet Gunes" <gunesahm@hotmail.com> wrote:
> >
> > > Hello,
> > >
> > > For a specific resource I try to change the status of a weekend to
> > > "Nondefault working time".
> > > Although in the "Resource Information" dialog everything seems ok,
I
> still
> > > can not assign a task to that resource for weekends.
> > > I use the same calendar both for the task and the resource.
> > >
> > > Can anybody help?
> > >
> > > Thanks,
> > >
> > > AHMET
> >
> > AHNET,
> > Your post says you "tried" to make the weekends as working time for
that
> > specific resource. Well, is it or is it not? Does the Working Time
tab
> > of the Resource Information dialogue for that resource show weekends
as
> > "nondefault working time"?
> >
> > Did you assign that resource to a task that bridges a weekend? What
> > makes you think that resource is not assigned for weekend work on
> > his/her tasks (look at the Resource Usage view)?
> >
> > John
> > Project MVP
>
>
>
>



Re: Why "Nondefault working time" does not work? by Jan

Jan
Tue Jul 04 11:36:06 CDT 2006

Hi,

A task calendar is a badse calendar, a resourece calendatr is not.
So it's a bit suspect when you say you use the same for both.
Isn't the task calendar the project calendar which gives nonworking time
that weekend?
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Ahmet Gunes" <gunesahm@hotmail.com> schreef in bericht
news:OHh1lfznGHA.3320@TK2MSFTNGP04.phx.gbl...
> Hello,
>
> For a specific resource I try to change the status of a weekend to
> "Nondefault working time".
> Although in the "Resource Information" dialog everything seems ok, I still
> can not assign a task to that resource for weekends.
> I use the same calendar both for the task and the resource.
>
> Can anybody help?
>
> Thanks,
>
> AHMET
>
>



Re: Why "Nondefault working time" does not work? by John

John
Tue Jul 04 22:05:58 CDT 2006

In article <eAdNnR4nGHA.3348@TK2MSFTNGP03.phx.gbl>,
"Ahmet Gunes" <gunesahm@hotmail.com> wrote:

> Hello John,
>
> In the Resource Information dialog everything seems ok. That's the weekend
> is marked as nondefault working time.
> When I try to assign a task to a resource for this weekend I get the message
> "You moved 'Task xxx' to a nonworking day".
>
> Thanks,
>
> AG

Ahmet,
Actually it's the other way around, resources are assigned to tasks,
tasks aren't assigned to resources. How exactly did you make the
assignment? The normal way is to select the task and then bring up the
Assign Resources window (two heads icon or Tools/Assign Resources).

If indeed you created a custom calendar for that resource and made
his/her weekends working days, then that resource can be assigned to any
task and weekends will be shown as working even if the task itself has a
normal calendar (i.e. weekends are non-working time). However also
changing the task calendar to make weekends working time will be more
consistent.

John
Project MVP
>
>
>
> "John" <mjensen@theriver.com> wrote in message
> news:mjensen-755316.08094104072006@msnews.microsoft.com...
> > In article <OHh1lfznGHA.3320@TK2MSFTNGP04.phx.gbl>,
> > "Ahmet Gunes" <gunesahm@hotmail.com> wrote:
> >
> > > Hello,
> > >
> > > For a specific resource I try to change the status of a weekend to
> > > "Nondefault working time".
> > > Although in the "Resource Information" dialog everything seems ok, I
> still
> > > can not assign a task to that resource for weekends.
> > > I use the same calendar both for the task and the resource.
> > >
> > > Can anybody help?
> > >
> > > Thanks,
> > >
> > > AHMET
> >
> > AHNET,
> > Your post says you "tried" to make the weekends as working time for that
> > specific resource. Well, is it or is it not? Does the Working Time tab
> > of the Resource Information dialogue for that resource show weekends as
> > "nondefault working time"?
> >
> > Did you assign that resource to a task that bridges a weekend? What
> > makes you think that resource is not assigned for weekend work on
> > his/her tasks (look at the Resource Usage view)?
> >
> > John
> > Project MVP