Mike
Thu Apr 17 14:27:03 CDT 2008
Hi Jeroen ,
Welcome to this Microsoft Project newsgroup :)
You can define 5 different cost rates per resource, each of which could have
a different overtime rate, in the Resource Information dialog (double click
the resource name in the Resource Sheet to set this up). You assign the
cost rate via the Resource Usage view with a double click on the task and
select the Cost rate table.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
Jeroen wrote:
> Is it possible to work with more then one overtime rate? Ik want to
> work with 100% 125% 150% 175% 200% and 250%. I need to plan with
> overtime sometimes so i want these rate to calculate exactly.