Hello,

I'm trying to generate a gantt chart with more than 5 non-workin
times. (essentially a 24-hour day with a 1-hour break every 4 hours).
MS Project only allows me to define 5 periods of "working times."
Anyone know how to create more

--
duckma
-----------------------------------------------------------------------
duckman's Profile: http://forums.techarena.in/member.php?userid=4952
View this thread: http://forums.techarena.in/showthread.php?t=96955

http://forums.techarena.i

Re: More than 5 non-working times by Jack

Jack
Fri May 16 14:51:39 CDT 2008

I do not believe that you can create more.
Is it that important to preserve the exact break times? You could create
resource calendars for each shift and apply them to the resource working on
each period or something similar for tasks. But it might just be easier to
group the breaks together.

-Jack Dahlgren

"duckman" <duckman.39imnd@DoNotSpam.com> wrote in message
news:duckman.39imnd@DoNotSpam.com...
>
> Hello,
>
> I'm trying to generate a gantt chart with more than 5 non-working
> times. (essentially a 24-hour day with a 1-hour break every 4 hours).
> MS Project only allows me to define 5 periods of "working times."
> Anyone know how to create more?
>
>
> --
> duckman
> ------------------------------------------------------------------------
> duckman's Profile: http://forums.techarena.in/member.php?userid=49525
> View this thread: http://forums.techarena.in/showthread.php?t=969557
>
> http://forums.techarena.in
>



Re: More than 5 non-working times by Steve

Steve
Sat May 17 10:27:06 CDT 2008

Do you resources actually work that sort of pattern - not as an aggregate
but each single resource viewed individually. The pattern you are
attempting to create suggests that the people working on your project never
get to sleep or have any other time off, just a meal break every 4 hours,
going on for day after day after day. Is that really what your resources
do?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"duckman" <duckman.39imnd@DoNotSpam.com> wrote in message
news:duckman.39imnd@DoNotSpam.com...
>
> Hello,
>
> I'm trying to generate a gantt chart with more than 5 non-working
> times. (essentially a 24-hour day with a 1-hour break every 4 hours).
> MS Project only allows me to define 5 periods of "working times."
> Anyone know how to create more?
>
>
> --
> duckman
> ------------------------------------------------------------------------
> duckman's Profile: http://forums.techarena.in/member.php?userid=49525
> View this thread: http://forums.techarena.in/showthread.php?t=969557
>
> http://forums.techarena.in
>