You do not need to spilt the task. Just go to the views menu. select the
"task usage" view or "resource usage" view and enter the work directly in
the cells for those days.
-Jack Dahlgre
http://zo-d.com/blog
"jen m" <jen m@discussions.microsoft.com> wrote in message
news:752CFD72-394D-4777-97B2-B502BF0A444A@microsoft.com...
>I am trying to split a task that has 12 hours so far split over several
>days.
> I am trying to show that 4.5hrs were put on the task the first day, 6.5
> the
> second day and 2 hrs the 3rd day plus there are a few more hours of work
> remaining. How do I split the task this way?