Hi Nerimo,
Welcome to this Microsoft Project newsgroup :)
There is no Average Cost field. However, you could insert a Cost field eg
Cost1 and put a formula in it like Cost + Overtime Cost / Work.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
"" <Nerimo@discussions.microsoft.com> wrote in message
news:830D88F2-AC3A-4A25-A029-93F93E33AA8F@microsoft.com...
>I have added a Standard Cost and an Overtime Cost for my resources, but
>also
> want to add an Average Cost, but I can't find another column to add to the
> Gantt that seems to be usable for this. Hoping someone may know a way.
> Thx!