ABG
Sat Nov 05 04:26:03 CST 2005
Thanks Dale, that's what I wanted to know!
You are right, I should have posted this under Project Server newsgroup. oops!
"Dale Howard [MVP]" wrote:
> ABC --
>
> I suspect that you are referring to the Maximum number of hours field on the
> Tracking settings page in PWA. If this is the case, I would recommend that
> you set the value to 24 hours. Also, in the future please post your Project
> Server questions in the microsoft.public.project.server newsgroup, as this
> newsgroup is devoted to the Microsoft Project desktop application only.
> Hope this helps.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
>
http://www.msprojectexperts.com
>
http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
> "ABG" <ABG@discussions.microsoft.com> wrote in message
> news:3223CDA7-FB4E-4D51-8F72-B0052C2C5475@microsoft.com...
> >I would like to know what is the standard used by other users when setting
> >up
> > a Maximum number of hours allowed per day. We were thinking of leaving it
> > with about 16 hours (just in case), but if someone needs to enter more
> > hours,
> > is there a way to override that value on the fly? or the default will need
> > to
> > be changed?. I am just curious.
> >
> > Thanks in advance!
>
>
>