As part of some resource plannig we're doing, I'd like to be able to
manually allocate effort to resources over the following few months.

For example, ResourceA will have 21 days assigned to TaskA, and I want him
to be assigned for 5 days in the first month, 4 days in the second month, 10
days in the third month and 2 days in the fourth month. I can't for the life
of me figure out how to do this in Project, alothugh I recall being able to
do this in ABT's (now Niku's) PMW/Workbench.

Thanks in advance for any help!
Roger

Re: Manually allocating time over several months by Jan

Jan
Tue Jul 26 03:25:42 CDT 2005

Hi,

Task Usage View
Set Bottom Tier of timescale to months.
Go.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Roger" <Roger@discussions.microsoft.com> schreef in bericht
news:EE04D7B4-9A6B-4862-8887-56418AD8F5DF@microsoft.com...
> Hi,
> As part of some resource plannig we're doing, I'd like to be able to
> manually allocate effort to resources over the following few months.
>
> For example, ResourceA will have 21 days assigned to TaskA, and I want him
> to be assigned for 5 days in the first month, 4 days in the second month,
10
> days in the third month and 2 days in the fourth month. I can't for the
life
> of me figure out how to do this in Project, alothugh I recall being able
to
> do this in ABT's (now Niku's) PMW/Workbench.
>
> Thanks in advance for any help!
> Roger



Re: Manually allocating time over several months by Roger

Roger
Tue Jul 26 03:51:02 CDT 2005

Oh.. that's embarrassingly easy.

Thanks very much!

<Reminder to self - explore more views>

Regards,
Roger


"Jan De Messemaeker" wrote:

> Hi,
>
> Task Usage View
> Set Bottom Tier of timescale to months.
> Go.
> HTH
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> http://users.online.be/prom-ade/
> +32-495-300 620
> "Roger" <Roger@discussions.microsoft.com> schreef in bericht
> news:EE04D7B4-9A6B-4862-8887-56418AD8F5DF@microsoft.com...
> > Hi,
> > As part of some resource plannig we're doing, I'd like to be able to
> > manually allocate effort to resources over the following few months.
> >
> > For example, ResourceA will have 21 days assigned to TaskA, and I want him
> > to be assigned for 5 days in the first month, 4 days in the second month,
> 10
> > days in the third month and 2 days in the fourth month. I can't for the
> life
> > of me figure out how to do this in Project, alothugh I recall being able
> to
> > do this in ABT's (now Niku's) PMW/Workbench.
> >
> > Thanks in advance for any help!
> > Roger
>
>
>