For tasks entered in hrs, is it possible to change the summary task to
display different units e.g. days?

RE: MSProject - How to change summary task properties by MAT

MAT
Tue Mar 28 07:56:03 CST 2006

Hi..
Its possible..
If you now give the duration automatic in hours then that means in your
standard settings the durationstarndsrt in hour.
So make the the standart entry for the duration as day. Noe if you enter
the duration it will be automatic day for all tasks..If you give the duration
for subtasks hour (MANUAL for examle task1: 16 h) then you will have the
duration of substaks hor and the duration of summaray task in day..
I hope this helps.