Hi Liz,
You can't completely prevent,but almost.
In tools, options, general, cross out
"Automatically add new reources and tasks"
After that when someone makes typo in the resporce names field thater will
be a warning message.
It is still possible to force the entry as a new resource but one will not
do it accidentally.
Hope this helps,
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"Liz W" <Liz W@discussions.microsoft.com> schreef in bericht
news:75CED5BC-0FCC-42D5-98FC-6C93364354F8@microsoft.com...
> I would like limit use of resources to only those that are listed on the
> Resource Sheet. Currently, names typed incorrectly whilst in the Gantt
Chart
> view are saved as a new resource. How can I prevent this?