Many of you know there is a "bug" in MS Project that affects the late dates
and backward pass.

If you indent a group of tasks under the summary task the late dates for
that group are changed by the summary task. A weird problem that only
surfaces when calculating total slack and the backward pass.

I've heard of some people using MSO/MFO anchors at the end of thier network
to solve this. Does anybody else have a solution. My company (a rather
large one) has submitted this to Microsoft and they acknowledge that it is a
bug, but aren't planning on fixing it anytime soon.

Please advise.

Sean

Re: Late Dates incorrect after indenting under Summary Task by JackD

JackD
Fri Feb 18 13:17:11 CST 2005

It is not entirely clear what you are talking about or what sort of advice
you are looking for.

Total slack is calculated whenever the schedule is recalculated (for those
who have calculation set to automatic - like me) a recalc occurs every time
a change is made to a schedule duration or link so to say it only occurs
when this happens is to assert that it occurs constantly.

There are some issues with linking to summary tasks, but I don't know that
I'd characterize them as a bug. Perhaps if you can give a more concrete idea
of what you are trying to say and some steps to reproduce it someone here
can help.

What is your problem specifically?


--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Sean" <Sean@discussions.microsoft.com> wrote in message
news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> Many of you know there is a "bug" in MS Project that affects the late
dates
> and backward pass.
>
> If you indent a group of tasks under the summary task the late dates for
> that group are changed by the summary task. A weird problem that only
> surfaces when calculating total slack and the backward pass.
>
> I've heard of some people using MSO/MFO anchors at the end of thier
network
> to solve this. Does anybody else have a solution. My company (a rather
> large one) has submitted this to Microsoft and they acknowledge that it is
a
> bug, but aren't planning on fixing it anytime soon.
>
> Please advise.
>
> Sean
>



Re: Late Dates incorrect after indenting under Summary Task by Steve

Steve
Sat Feb 19 07:24:57 CST 2005

I'm not aware of any "bug" like you're describing. The total slack time of
a task is the amount of time it could be delayed without delaying the
project finish, in a nutshell. Imagine Summary Task A with subtasks A1
(3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in
parallel, all starting the same day. Summary task A links to Summary X FS
and Summary X in turn links FS to the Finish milestone. What are the late
dates of A1, A2, & A3? Summary A's finish is determined by A3 so the late
date of A3 and Summary A are the same. Only if Summary A is delayed past
that point will Summary X be delayed, hence that is also the latest date it
can finish without delaying the project's finish. The late finishes of A1
and A2 are also that same date as A3 (which is also the late finish of
Summary A), since they could slip by 2 or 1 day respectively before they
delay the finish of Summary A. I think that is what you're describing in
your posting but where's the bug in that? That is exactly the way late
starts and late finishes are supposed to be calculated and that's the way
project does calculate them. And this is even with linking between the
summary tasks, which is often considered a bad idea. The alternative
linking would have A1, A2, and A3 all as predecessors to X1 and no links
directly in or out of the summary tasks themselves but the results are
exactly the same.

If I'm missing something here, please give us some concrete example that
demonstrates what you consider to be this bug - what Project gives you and
what you think it should be giving you instead (and why you feel Project is
wrong and your way is right). I'm really curious.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs





"Sean" <Sean@discussions.microsoft.com> wrote in message
news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> Many of you know there is a "bug" in MS Project that affects the late
> dates
> and backward pass.
>
> If you indent a group of tasks under the summary task the late dates for
> that group are changed by the summary task. A weird problem that only
> surfaces when calculating total slack and the backward pass.
>
> I've heard of some people using MSO/MFO anchors at the end of thier
> network
> to solve this. Does anybody else have a solution. My company (a rather
> large one) has submitted this to Microsoft and they acknowledge that it is
> a
> bug, but aren't planning on fixing it anytime soon.
>
> Please advise.
>
> Sean
>


Re: Late Dates incorrect after indenting under Summary Task by Sean

Sean
Wed Feb 23 09:59:08 CST 2005

Let me explain better.

Create a project with the following info. The summary task is not Linked.
Don't indent it under the summary until you've added all the tasks. All
relationships are FS. Use a 5 day duration for all tasks. Insert the late
start field into your table.

Now, indent all the tasks under the sumary task. Watch the late dates
change. They shouldn't becuase there is no link or relationship to the
summary line. Microsoft has acknowledged the problem but has made no promise
to fix it. I've heard of some work around's but not found one that is 100%

Thanks
Sean

ID NAME PRED
1 summary
2 Start Milestone #1
3 Activity #1 2
4 Activity #2 3
5 Activity #3 4
6 Finish Milestone #1 5,10
7 Start Milestone #2
8 Activity #4 7
9 Activity #5 8
10 Activity #6 9
11 Start Milestone # 3
12 Activity #7 11
13 Activity #8 12
14 Activity #9 13
15 Finish Milestone #2 14




"Steve House [MVP]" wrote:

> I'm not aware of any "bug" like you're describing. The total slack time of
> a task is the amount of time it could be delayed without delaying the
> project finish, in a nutshell. Imagine Summary Task A with subtasks A1
> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in
> parallel, all starting the same day. Summary task A links to Summary X FS
> and Summary X in turn links FS to the Finish milestone. What are the late
> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the late
> date of A3 and Summary A are the same. Only if Summary A is delayed past
> that point will Summary X be delayed, hence that is also the latest date it
> can finish without delaying the project's finish. The late finishes of A1
> and A2 are also that same date as A3 (which is also the late finish of
> Summary A), since they could slip by 2 or 1 day respectively before they
> delay the finish of Summary A. I think that is what you're describing in
> your posting but where's the bug in that? That is exactly the way late
> starts and late finishes are supposed to be calculated and that's the way
> project does calculate them. And this is even with linking between the
> summary tasks, which is often considered a bad idea. The alternative
> linking would have A1, A2, and A3 all as predecessors to X1 and no links
> directly in or out of the summary tasks themselves but the results are
> exactly the same.
>
> If I'm missing something here, please give us some concrete example that
> demonstrates what you consider to be this bug - what Project gives you and
> what you think it should be giving you instead (and why you feel Project is
> wrong and your way is right). I'm really curious.
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
>
>
>
> "Sean" <Sean@discussions.microsoft.com> wrote in message
> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> > Many of you know there is a "bug" in MS Project that affects the late
> > dates
> > and backward pass.
> >
> > If you indent a group of tasks under the summary task the late dates for
> > that group are changed by the summary task. A weird problem that only
> > surfaces when calculating total slack and the backward pass.
> >
> > I've heard of some people using MSO/MFO anchors at the end of thier
> > network
> > to solve this. Does anybody else have a solution. My company (a rather
> > large one) has submitted this to Microsoft and they acknowledge that it is
> > a
> > bug, but aren't planning on fixing it anytime soon.
> >
> > Please advise.
> >
> > Sean
> >
>
>

Re: Late Dates incorrect after indenting under Summary Task by JackD

JackD
Wed Feb 23 12:33:44 CST 2005

Um.... It works fine for me. There is no change. I can't reproduce your
problem.
Which version of project are you using?
Are all tasks set to be start as soon as possible?

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Sean" <Sean@discussions.microsoft.com> wrote in message
news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> Let me explain better.
>
> Create a project with the following info. The summary task is not Linked.
> Don't indent it under the summary until you've added all the tasks. All
> relationships are FS. Use a 5 day duration for all tasks. Insert the late
> start field into your table.
>
> Now, indent all the tasks under the sumary task. Watch the late dates
> change. They shouldn't becuase there is no link or relationship to the
> summary line. Microsoft has acknowledged the problem but has made no
promise
> to fix it. I've heard of some work around's but not found one that is
100%
>
> Thanks
> Sean
>
> ID NAME PRED
> 1 summary
> 2 Start Milestone #1
> 3 Activity #1 2
> 4 Activity #2 3
> 5 Activity #3 4
> 6 Finish Milestone #1 5,10
> 7 Start Milestone #2
> 8 Activity #4 7
> 9 Activity #5 8
> 10 Activity #6 9
> 11 Start Milestone # 3
> 12 Activity #7 11
> 13 Activity #8 12
> 14 Activity #9 13
> 15 Finish Milestone #2 14
>
>
>
>
> "Steve House [MVP]" wrote:
>
> > I'm not aware of any "bug" like you're describing. The total slack time
of
> > a task is the amount of time it could be delayed without delaying the
> > project finish, in a nutshell. Imagine Summary Task A with subtasks A1
> > (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in

> > parallel, all starting the same day. Summary task A links to Summary X
FS
> > and Summary X in turn links FS to the Finish milestone. What are the
late
> > dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
late
> > date of A3 and Summary A are the same. Only if Summary A is delayed
past
> > that point will Summary X be delayed, hence that is also the latest date
it
> > can finish without delaying the project's finish. The late finishes of
A1
> > and A2 are also that same date as A3 (which is also the late finish of
> > Summary A), since they could slip by 2 or 1 day respectively before they
> > delay the finish of Summary A. I think that is what you're describing
in
> > your posting but where's the bug in that? That is exactly the way late
> > starts and late finishes are supposed to be calculated and that's the
way
> > project does calculate them. And this is even with linking between the
> > summary tasks, which is often considered a bad idea. The alternative
> > linking would have A1, A2, and A3 all as predecessors to X1 and no links
> > directly in or out of the summary tasks themselves but the results are
> > exactly the same.
> >
> > If I'm missing something here, please give us some concrete example that
> > demonstrates what you consider to be this bug - what Project gives you
and
> > what you think it should be giving you instead (and why you feel Project
is
> > wrong and your way is right). I'm really curious.
> > --
> > Steve House [MVP]
> > MS Project Trainer & Consultant
> > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >
> >
> >
> >
> >
> > "Sean" <Sean@discussions.microsoft.com> wrote in message
> > news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> > > Many of you know there is a "bug" in MS Project that affects the late
> > > dates
> > > and backward pass.
> > >
> > > If you indent a group of tasks under the summary task the late dates
for
> > > that group are changed by the summary task. A weird problem that only
> > > surfaces when calculating total slack and the backward pass.
> > >
> > > I've heard of some people using MSO/MFO anchors at the end of thier
> > > network
> > > to solve this. Does anybody else have a solution. My company (a
rather
> > > large one) has submitted this to Microsoft and they acknowledge that
it is
> > > a
> > > bug, but aren't planning on fixing it anytime soon.
> > >
> > > Please advise.
> > >
> > > Sean
> > >
> >
> >



Re: Late Dates incorrect after indenting under Summary Task by Steve

Steve
Wed Feb 23 12:51:24 CST 2005

Task 11, labeled "Start Milestone #", do you mean its predecessor is task #3
or do you mean its name is Start Milestone #3?

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Sean" <Sean@discussions.microsoft.com> wrote in message
news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> Let me explain better.
>
> Create a project with the following info. The summary task is not Linked.
> Don't indent it under the summary until you've added all the tasks. All
> relationships are FS. Use a 5 day duration for all tasks. Insert the late
> start field into your table.
>
> Now, indent all the tasks under the sumary task. Watch the late dates
> change. They shouldn't becuase there is no link or relationship to the
> summary line. Microsoft has acknowledged the problem but has made no
> promise
> to fix it. I've heard of some work around's but not found one that is
> 100%
>
> Thanks
> Sean
>
> ID NAME PRED
> 1 summary
> 2 Start Milestone #1
> 3 Activity #1 2
> 4 Activity #2 3
> 5 Activity #3 4
> 6 Finish Milestone #1 5,10
> 7 Start Milestone #2
> 8 Activity #4 7
> 9 Activity #5 8
> 10 Activity #6 9
> 11 Start Milestone # 3
> 12 Activity #7 11
> 13 Activity #8 12
> 14 Activity #9 13
> 15 Finish Milestone #2 14
>
>
>
>
> "Steve House [MVP]" wrote:
>
>> I'm not aware of any "bug" like you're describing. The total slack time
>> of
>> a task is the amount of time it could be delayed without delaying the
>> project finish, in a nutshell. Imagine Summary Task A with subtasks A1
>> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in
>> parallel, all starting the same day. Summary task A links to Summary X
>> FS
>> and Summary X in turn links FS to the Finish milestone. What are the
>> late
>> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
>> late
>> date of A3 and Summary A are the same. Only if Summary A is delayed past
>> that point will Summary X be delayed, hence that is also the latest date
>> it
>> can finish without delaying the project's finish. The late finishes of
>> A1
>> and A2 are also that same date as A3 (which is also the late finish of
>> Summary A), since they could slip by 2 or 1 day respectively before they
>> delay the finish of Summary A. I think that is what you're describing in
>> your posting but where's the bug in that? That is exactly the way late
>> starts and late finishes are supposed to be calculated and that's the way
>> project does calculate them. And this is even with linking between the
>> summary tasks, which is often considered a bad idea. The alternative
>> linking would have A1, A2, and A3 all as predecessors to X1 and no links
>> directly in or out of the summary tasks themselves but the results are
>> exactly the same.
>>
>> If I'm missing something here, please give us some concrete example that
>> demonstrates what you consider to be this bug - what Project gives you
>> and
>> what you think it should be giving you instead (and why you feel Project
>> is
>> wrong and your way is right). I'm really curious.
>> --
>> Steve House [MVP]
>> MS Project Trainer & Consultant
>> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>>
>>
>>
>>
>>
>> "Sean" <Sean@discussions.microsoft.com> wrote in message
>> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
>> > Many of you know there is a "bug" in MS Project that affects the late
>> > dates
>> > and backward pass.
>> >
>> > If you indent a group of tasks under the summary task the late dates
>> > for
>> > that group are changed by the summary task. A weird problem that only
>> > surfaces when calculating total slack and the backward pass.
>> >
>> > I've heard of some people using MSO/MFO anchors at the end of thier
>> > network
>> > to solve this. Does anybody else have a solution. My company (a
>> > rather
>> > large one) has submitted this to Microsoft and they acknowledge that it
>> > is
>> > a
>> > bug, but aren't planning on fixing it anytime soon.
>> >
>> > Please advise.
>> >
>> > Sean
>> >
>>
>>


Re: Late Dates incorrect after indenting under Summary Task by Steve

Steve
Wed Feb 23 13:01:46 CST 2005

Using Project 2003 Pro with all service packs up to date. I just asked
about task 11's predecessor, but then I tried it both ways - no predecessor
for task 11 or Activity 3 FS to Task 11. Either way I get no change in the
late start dates for any of the tasks whether they're indented under the
summary or not. I followed your directions to the letter, re-check your
message quoted below to make sure there's no typo that lead me someplace
other than where you intended.

There are no other tasks in the project. When you say indent under the
summary, you are NOT indenting task 1 labeled "summary" but are indenting
tasks 2 though 15, right?

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"Sean" <Sean@discussions.microsoft.com> wrote in message
news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> Let me explain better.
>
> Create a project with the following info. The summary task is not Linked.
> Don't indent it under the summary until you've added all the tasks. All
> relationships are FS. Use a 5 day duration for all tasks. Insert the late
> start field into your table.
>
> Now, indent all the tasks under the sumary task. Watch the late dates
> change. They shouldn't becuase there is no link or relationship to the
> summary line. Microsoft has acknowledged the problem but has made no
> promise
> to fix it. I've heard of some work around's but not found one that is
> 100%
>
> Thanks
> Sean
>
> ID NAME PRED
> 1 summary
> 2 Start Milestone #1
> 3 Activity #1 2
> 4 Activity #2 3
> 5 Activity #3 4
> 6 Finish Milestone #1 5,10
> 7 Start Milestone #2
> 8 Activity #4 7
> 9 Activity #5 8
> 10 Activity #6 9
> 11 Start Milestone # 3
> 12 Activity #7 11
> 13 Activity #8 12
> 14 Activity #9 13
> 15 Finish Milestone #2 14
>
>
>
>
> "Steve House [MVP]" wrote:
>
>> I'm not aware of any "bug" like you're describing. The total slack time
>> of
>> a task is the amount of time it could be delayed without delaying the
>> project finish, in a nutshell. Imagine Summary Task A with subtasks A1
>> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in
>> parallel, all starting the same day. Summary task A links to Summary X
>> FS
>> and Summary X in turn links FS to the Finish milestone. What are the
>> late
>> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
>> late
>> date of A3 and Summary A are the same. Only if Summary A is delayed past
>> that point will Summary X be delayed, hence that is also the latest date
>> it
>> can finish without delaying the project's finish. The late finishes of
>> A1
>> and A2 are also that same date as A3 (which is also the late finish of
>> Summary A), since they could slip by 2 or 1 day respectively before they
>> delay the finish of Summary A. I think that is what you're describing in
>> your posting but where's the bug in that? That is exactly the way late
>> starts and late finishes are supposed to be calculated and that's the way
>> project does calculate them. And this is even with linking between the
>> summary tasks, which is often considered a bad idea. The alternative
>> linking would have A1, A2, and A3 all as predecessors to X1 and no links
>> directly in or out of the summary tasks themselves but the results are
>> exactly the same.
>>
>> If I'm missing something here, please give us some concrete example that
>> demonstrates what you consider to be this bug - what Project gives you
>> and
>> what you think it should be giving you instead (and why you feel Project
>> is
>> wrong and your way is right). I'm really curious.
>> --
>> Steve House [MVP]
>> MS Project Trainer & Consultant
>> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>>
>>
>>
>>
>>
>> "Sean" <Sean@discussions.microsoft.com> wrote in message
>> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
>> > Many of you know there is a "bug" in MS Project that affects the late
>> > dates
>> > and backward pass.
>> >
>> > If you indent a group of tasks under the summary task the late dates
>> > for
>> > that group are changed by the summary task. A weird problem that only
>> > surfaces when calculating total slack and the backward pass.
>> >
>> > I've heard of some people using MSO/MFO anchors at the end of thier
>> > network
>> > to solve this. Does anybody else have a solution. My company (a
>> > rather
>> > large one) has submitted this to Microsoft and they acknowledge that it
>> > is
>> > a
>> > bug, but aren't planning on fixing it anytime soon.
>> >
>> > Please advise.
>> >
>> > Sean
>> >
>>
>>


Re: Late Dates incorrect after indenting under Summary Task by Sean

Sean
Mon Feb 28 16:45:02 CST 2005

Okay, Sorry for the confusion. Forgot the critical part of constraints.
Make a quick network with the project start date of 2/28/05.

Name Dur Pred Constraint Type Constraint date
Summary 1 day? ASAP NA
Start Milestone One 0 days SNET 3/10/2005
Task One 5 days 2 ASAP NA
Task Two 5 days 3 ASAP NA
Task Three 5 days 4 ASAP NA
Task Four 5 days 5 ASAP NA
Finish Milestone 0 days 6 FNLT 5/19/2005

Insert the late start field. After you've entered in the network highlight
and indent everything under the summary task. The late start will change.


"Steve House [MVP]" wrote:

> Using Project 2003 Pro with all service packs up to date. I just asked
> about task 11's predecessor, but then I tried it both ways - no predecessor
> for task 11 or Activity 3 FS to Task 11. Either way I get no change in the
> late start dates for any of the tasks whether they're indented under the
> summary or not. I followed your directions to the letter, re-check your
> message quoted below to make sure there's no typo that lead me someplace
> other than where you intended.
>
> There are no other tasks in the project. When you say indent under the
> summary, you are NOT indenting task 1 labeled "summary" but are indenting
> tasks 2 though 15, right?
>
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
>
> "Sean" <Sean@discussions.microsoft.com> wrote in message
> news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> > Let me explain better.
> >
> > Create a project with the following info. The summary task is not Linked.
> > Don't indent it under the summary until you've added all the tasks. All
> > relationships are FS. Use a 5 day duration for all tasks. Insert the late
> > start field into your table.
> >
> > Now, indent all the tasks under the sumary task. Watch the late dates
> > change. They shouldn't becuase there is no link or relationship to the
> > summary line. Microsoft has acknowledged the problem but has made no
> > promise
> > to fix it. I've heard of some work around's but not found one that is
> > 100%
> >
> > Thanks
> > Sean
> >
> > ID NAME PRED
> > 1 summary
> > 2 Start Milestone #1
> > 3 Activity #1 2
> > 4 Activity #2 3
> > 5 Activity #3 4
> > 6 Finish Milestone #1 5,10
> > 7 Start Milestone #2
> > 8 Activity #4 7
> > 9 Activity #5 8
> > 10 Activity #6 9
> > 11 Start Milestone # 3
> > 12 Activity #7 11
> > 13 Activity #8 12
> > 14 Activity #9 13
> > 15 Finish Milestone #2 14
> >
> >
> >
> >
> > "Steve House [MVP]" wrote:
> >
> >> I'm not aware of any "bug" like you're describing. The total slack time
> >> of
> >> a task is the amount of time it could be delayed without delaying the
> >> project finish, in a nutshell. Imagine Summary Task A with subtasks A1
> >> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in
> >> parallel, all starting the same day. Summary task A links to Summary X
> >> FS
> >> and Summary X in turn links FS to the Finish milestone. What are the
> >> late
> >> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
> >> late
> >> date of A3 and Summary A are the same. Only if Summary A is delayed past
> >> that point will Summary X be delayed, hence that is also the latest date
> >> it
> >> can finish without delaying the project's finish. The late finishes of
> >> A1
> >> and A2 are also that same date as A3 (which is also the late finish of
> >> Summary A), since they could slip by 2 or 1 day respectively before they
> >> delay the finish of Summary A. I think that is what you're describing in
> >> your posting but where's the bug in that? That is exactly the way late
> >> starts and late finishes are supposed to be calculated and that's the way
> >> project does calculate them. And this is even with linking between the
> >> summary tasks, which is often considered a bad idea. The alternative
> >> linking would have A1, A2, and A3 all as predecessors to X1 and no links
> >> directly in or out of the summary tasks themselves but the results are
> >> exactly the same.
> >>
> >> If I'm missing something here, please give us some concrete example that
> >> demonstrates what you consider to be this bug - what Project gives you
> >> and
> >> what you think it should be giving you instead (and why you feel Project
> >> is
> >> wrong and your way is right). I'm really curious.
> >> --
> >> Steve House [MVP]
> >> MS Project Trainer & Consultant
> >> Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >>
> >>
> >>
> >>
> >>
> >> "Sean" <Sean@discussions.microsoft.com> wrote in message
> >> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> >> > Many of you know there is a "bug" in MS Project that affects the late
> >> > dates
> >> > and backward pass.
> >> >
> >> > If you indent a group of tasks under the summary task the late dates
> >> > for
> >> > that group are changed by the summary task. A weird problem that only
> >> > surfaces when calculating total slack and the backward pass.
> >> >
> >> > I've heard of some people using MSO/MFO anchors at the end of thier
> >> > network
> >> > to solve this. Does anybody else have a solution. My company (a
> >> > rather
> >> > large one) has submitted this to Microsoft and they acknowledge that it
> >> > is
> >> > a
> >> > bug, but aren't planning on fixing it anytime soon.
> >> >
> >> > Please advise.
> >> >
> >> > Sean
> >> >
> >>
> >>
>
>

Re: Late Dates incorrect after indenting under Summary Task by JackD

JackD
Mon Feb 28 18:06:55 CST 2005

Hm.
Another reason to avoid constraints.
Of course the workaround is to put the task with the finish constraint
outside the summary task. Is that what Microsoft advised you to do?

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Sean" <Sean@discussions.microsoft.com> wrote in message
news:3AE2FAA1-12AE-421C-8B5E-D223D2605338@microsoft.com...
> Okay, Sorry for the confusion. Forgot the critical part of constraints.
> Make a quick network with the project start date of 2/28/05.
>
> Name Dur Pred Constraint Type Constraint date
> Summary 1 day? ASAP NA
> Start Milestone One 0 days SNET 3/10/2005
> Task One 5 days 2 ASAP NA
> Task Two 5 days 3 ASAP NA
> Task Three 5 days 4 ASAP NA
> Task Four 5 days 5 ASAP NA
> Finish Milestone 0 days 6 FNLT 5/19/2005
>
> Insert the late start field. After you've entered in the network
highlight
> and indent everything under the summary task. The late start will change.
>
>
> "Steve House [MVP]" wrote:
>
> > Using Project 2003 Pro with all service packs up to date. I just asked
> > about task 11's predecessor, but then I tried it both ways - no
predecessor
> > for task 11 or Activity 3 FS to Task 11. Either way I get no change in
the
> > late start dates for any of the tasks whether they're indented under the
> > summary or not. I followed your directions to the letter, re-check your
> > message quoted below to make sure there's no typo that lead me someplace
> > other than where you intended.
> >
> > There are no other tasks in the project. When you say indent under the
> > summary, you are NOT indenting task 1 labeled "summary" but are
indenting
> > tasks 2 though 15, right?
> >
> > --
> > Steve House [MVP]
> > MS Project Trainer & Consultant
> > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >
> >
> >
> > "Sean" <Sean@discussions.microsoft.com> wrote in message
> > news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> > > Let me explain better.
> > >
> > > Create a project with the following info. The summary task is not
Linked.
> > > Don't indent it under the summary until you've added all the tasks.
All
> > > relationships are FS. Use a 5 day duration for all tasks. Insert the
late
> > > start field into your table.
> > >
> > > Now, indent all the tasks under the sumary task. Watch the late dates
> > > change. They shouldn't becuase there is no link or relationship to
the
> > > summary line. Microsoft has acknowledged the problem but has made no
> > > promise
> > > to fix it. I've heard of some work around's but not found one that is
> > > 100%
> > >
> > > Thanks
> > > Sean
> > >
> > > ID NAME PRED
> > > 1 summary
> > > 2 Start Milestone #1
> > > 3 Activity #1 2
> > > 4 Activity #2 3
> > > 5 Activity #3 4
> > > 6 Finish Milestone #1 5,10
> > > 7 Start Milestone #2
> > > 8 Activity #4 7
> > > 9 Activity #5 8
> > > 10 Activity #6 9
> > > 11 Start Milestone # 3
> > > 12 Activity #7 11
> > > 13 Activity #8 12
> > > 14 Activity #9 13
> > > 15 Finish Milestone #2 14
> > >
> > >
> > >
> > >
> > > "Steve House [MVP]" wrote:
> > >
> > >> I'm not aware of any "bug" like you're describing. The total slack
time
> > >> of
> > >> a task is the amount of time it could be delayed without delaying the
> > >> project finish, in a nutshell. Imagine Summary Task A with subtasks
A1
> > >> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur
in
> > >> parallel, all starting the same day. Summary task A links to Summary
X
> > >> FS
> > >> and Summary X in turn links FS to the Finish milestone. What are the
> > >> late
> > >> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
> > >> late
> > >> date of A3 and Summary A are the same. Only if Summary A is delayed
past
> > >> that point will Summary X be delayed, hence that is also the latest
date
> > >> it
> > >> can finish without delaying the project's finish. The late finishes
of
> > >> A1
> > >> and A2 are also that same date as A3 (which is also the late finish
of
> > >> Summary A), since they could slip by 2 or 1 day respectively before
they
> > >> delay the finish of Summary A. I think that is what you're
describing in
> > >> your posting but where's the bug in that? That is exactly the way
late
> > >> starts and late finishes are supposed to be calculated and that's the
way
> > >> project does calculate them. And this is even with linking between
the
> > >> summary tasks, which is often considered a bad idea. The alternative
> > >> linking would have A1, A2, and A3 all as predecessors to X1 and no
links
> > >> directly in or out of the summary tasks themselves but the results
are
> > >> exactly the same.
> > >>
> > >> If I'm missing something here, please give us some concrete example
that
> > >> demonstrates what you consider to be this bug - what Project gives
you
> > >> and
> > >> what you think it should be giving you instead (and why you feel
Project
> > >> is
> > >> wrong and your way is right). I'm really curious.
> > >> --
> > >> Steve House [MVP]
> > >> MS Project Trainer & Consultant
> > >> Visit http://www.mvps.org/project/faqs.htm for the FAQs
> > >>
> > >>
> > >>
> > >>
> > >>
> > >> "Sean" <Sean@discussions.microsoft.com> wrote in message
> > >> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> > >> > Many of you know there is a "bug" in MS Project that affects the
late
> > >> > dates
> > >> > and backward pass.
> > >> >
> > >> > If you indent a group of tasks under the summary task the late
dates
> > >> > for
> > >> > that group are changed by the summary task. A weird problem that
only
> > >> > surfaces when calculating total slack and the backward pass.
> > >> >
> > >> > I've heard of some people using MSO/MFO anchors at the end of thier
> > >> > network
> > >> > to solve this. Does anybody else have a solution. My company (a
> > >> > rather
> > >> > large one) has submitted this to Microsoft and they acknowledge
that it
> > >> > is
> > >> > a
> > >> > bug, but aren't planning on fixing it anytime soon.
> > >> >
> > >> > Please advise.
> > >> >
> > >> > Sean
> > >> >
> > >>
> > >>
> >
> >



Re: Late Dates incorrect after indenting under Summary Task by Steve

Steve
Tue Mar 01 08:09:42 CST 2005

You problem is in the (IMHO incorrect) use of the FNLT constraint on the
Finish milestone to indicate your deadline. First of all, using a
constraint to indicate your deadline says that Project will never schedule
that task to end later than the date you've entered, even if that date is
impossible to meet. When you work the schedule you *will* be late. Usiong
a deadline entry instead, OTOH, marks the plan where that task needs to hit
but it does NOT disable Project's ability to show you where it currently
will actually end up. If the schedule as planned results in your missing
the required finish date, the deadline shows you that fact directly AND
shows you how bad you've blown it. The constraint will show you finishing
on your deadline whether you're actually going to do that or not and to see
you've got a problem you have to add columns to monitor the slack time.

As an aside, I can see many examples where a SNET constraint might be a
valid model of reality - a supplier might not be able to deliver required
parts for the subject task before a certain date, for example - but I've
wracked my mind over and over and I have yet to come up with a real world
example where a FNLT constraint, as opposed to a Finish Deadline, would be
the appropriate setting. The FNLT constraint says, in effect - "If this
task hasn't already happened by xx/xx/xx date, it absolutely, positively,
WILL happen on that date regardless of anything you do" (note "will" and not
"should" - constraints imply established facts while deadlines imply
requirements) and I just can't think of anything in the real world that
behaves that way.

More to the point, when you indent the tasks, including the finish
milestone, under the summary, the deadline then really is when the summary
needs to finish. The deadline date is an attribute of the summary task
itself and is not directly associated with a specific task within it. In
your example, if you put the deadline or FNLT constraint of 5/19 to the
summary task and not the finish milestone and then work out by hand the Late
Finish dates of the subtasks once you've indented them, you'll find
Project's calculated dates will be correct.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Sean" <Sean@discussions.microsoft.com> wrote in message
news:3AE2FAA1-12AE-421C-8B5E-D223D2605338@microsoft.com...
> Okay, Sorry for the confusion. Forgot the critical part of constraints.
> Make a quick network with the project start date of 2/28/05.
>
> Name Dur Pred Constraint Type Constraint date
> Summary 1 day? ASAP NA
> Start Milestone One 0 days SNET 3/10/2005
> Task One 5 days 2 ASAP NA
> Task Two 5 days 3 ASAP NA
> Task Three 5 days 4 ASAP NA
> Task Four 5 days 5 ASAP NA
> Finish Milestone 0 days 6 FNLT 5/19/2005
>
> Insert the late start field. After you've entered in the network
> highlight
> and indent everything under the summary task. The late start will change.
>
>
> "Steve House [MVP]" wrote:
>
>> Using Project 2003 Pro with all service packs up to date. I just asked
>> about task 11's predecessor, but then I tried it both ways - no
>> predecessor
>> for task 11 or Activity 3 FS to Task 11. Either way I get no change in
>> the
>> late start dates for any of the tasks whether they're indented under the
>> summary or not. I followed your directions to the letter, re-check your
>> message quoted below to make sure there's no typo that lead me someplace
>> other than where you intended.
>>
>> There are no other tasks in the project. When you say indent under the
>> summary, you are NOT indenting task 1 labeled "summary" but are indenting
>> tasks 2 though 15, right?
>>
>> --
>> Steve House [MVP]
>> MS Project Trainer & Consultant
>> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>>
>>
>>
>> "Sean" <Sean@discussions.microsoft.com> wrote in message
>> news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
>> > Let me explain better.
>> >
>> > Create a project with the following info. The summary task is not
>> > Linked.
>> > Don't indent it under the summary until you've added all the tasks.
>> > All
>> > relationships are FS. Use a 5 day duration for all tasks. Insert the
>> > late
>> > start field into your table.
>> >
>> > Now, indent all the tasks under the sumary task. Watch the late dates
>> > change. They shouldn't becuase there is no link or relationship to the
>> > summary line. Microsoft has acknowledged the problem but has made no
>> > promise
>> > to fix it. I've heard of some work around's but not found one that is
>> > 100%
>> >
>> > Thanks
>> > Sean
>> >
>> > ID NAME PRED
>> > 1 summary
>> > 2 Start Milestone #1
>> > 3 Activity #1 2
>> > 4 Activity #2 3
>> > 5 Activity #3 4
>> > 6 Finish Milestone #1 5,10
>> > 7 Start Milestone #2
>> > 8 Activity #4 7
>> > 9 Activity #5 8
>> > 10 Activity #6 9
>> > 11 Start Milestone # 3
>> > 12 Activity #7 11
>> > 13 Activity #8 12
>> > 14 Activity #9 13
>> > 15 Finish Milestone #2 14
>> >
>> >
>> >
>> >
>> > "Steve House [MVP]" wrote:
>> >
>> >> I'm not aware of any "bug" like you're describing. The total slack
>> >> time
>> >> of
>> >> a task is the amount of time it could be delayed without delaying the
>> >> project finish, in a nutshell. Imagine Summary Task A with subtasks
>> >> A1
>> >> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur
>> >> in
>> >> parallel, all starting the same day. Summary task A links to Summary
>> >> X
>> >> FS
>> >> and Summary X in turn links FS to the Finish milestone. What are the
>> >> late
>> >> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
>> >> late
>> >> date of A3 and Summary A are the same. Only if Summary A is delayed
>> >> past
>> >> that point will Summary X be delayed, hence that is also the latest
>> >> date
>> >> it
>> >> can finish without delaying the project's finish. The late finishes
>> >> of
>> >> A1
>> >> and A2 are also that same date as A3 (which is also the late finish of
>> >> Summary A), since they could slip by 2 or 1 day respectively before
>> >> they
>> >> delay the finish of Summary A. I think that is what you're describing
>> >> in
>> >> your posting but where's the bug in that? That is exactly the way
>> >> late
>> >> starts and late finishes are supposed to be calculated and that's the
>> >> way
>> >> project does calculate them. And this is even with linking between
>> >> the
>> >> summary tasks, which is often considered a bad idea. The alternative
>> >> linking would have A1, A2, and A3 all as predecessors to X1 and no
>> >> links
>> >> directly in or out of the summary tasks themselves but the results are
>> >> exactly the same.
>> >>
>> >> If I'm missing something here, please give us some concrete example
>> >> that
>> >> demonstrates what you consider to be this bug - what Project gives you
>> >> and
>> >> what you think it should be giving you instead (and why you feel
>> >> Project
>> >> is
>> >> wrong and your way is right). I'm really curious.
>> >> --
>> >> Steve House [MVP]
>> >> MS Project Trainer & Consultant
>> >> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>> >>
>> >>
>> >>
>> >>
>> >>
>> >> "Sean" <Sean@discussions.microsoft.com> wrote in message
>> >> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
>> >> > Many of you know there is a "bug" in MS Project that affects the
>> >> > late
>> >> > dates
>> >> > and backward pass.
>> >> >
>> >> > If you indent a group of tasks under the summary task the late dates
>> >> > for
>> >> > that group are changed by the summary task. A weird problem that
>> >> > only
>> >> > surfaces when calculating total slack and the backward pass.
>> >> >
>> >> > I've heard of some people using MSO/MFO anchors at the end of thier
>> >> > network
>> >> > to solve this. Does anybody else have a solution. My company (a
>> >> > rather
>> >> > large one) has submitted this to Microsoft and they acknowledge that
>> >> > it
>> >> > is
>> >> > a
>> >> > bug, but aren't planning on fixing it anytime soon.
>> >> >
>> >> > Please advise.
>> >> >
>> >> > Sean
>> >> >
>> >>
>> >>
>>
>>


Re: Late Dates incorrect after indenting under Summary Task by Sean

Sean
Tue Mar 01 08:21:05 CST 2005

Microsoft hasn't given any recommendations, they are exploring the fix to
thier "undesirable feature." If you don't use outlining it calcs correctly.
The other fix I've seen is to put a "ghost" node with a MSO after the end of
the last milestone and link it to the last FNLT. However, you have to do
this for each path through your network. On a 10,000 line file you now have
100 extra "ghost" milestones.

Don't mean for you to spend a lot of time on this, was just curious of
others encountered it and possibly had a workaround.

Thanks

"JackD" wrote:

> Hm.
> Another reason to avoid constraints.
> Of course the workaround is to put the task with the finish constraint
> outside the summary task. Is that what Microsoft advised you to do?
>
> --
> -Jack ... For project information and macro examples visit
> http://masamiki.com/project
>
> ..
> "Sean" <Sean@discussions.microsoft.com> wrote in message
> news:3AE2FAA1-12AE-421C-8B5E-D223D2605338@microsoft.com...
> > Okay, Sorry for the confusion. Forgot the critical part of constraints.
> > Make a quick network with the project start date of 2/28/05.
> >
> > Name Dur Pred Constraint Type Constraint date
> > Summary 1 day? ASAP NA
> > Start Milestone One 0 days SNET 3/10/2005
> > Task One 5 days 2 ASAP NA
> > Task Two 5 days 3 ASAP NA
> > Task Three 5 days 4 ASAP NA
> > Task Four 5 days 5 ASAP NA
> > Finish Milestone 0 days 6 FNLT 5/19/2005
> >
> > Insert the late start field. After you've entered in the network
> highlight
> > and indent everything under the summary task. The late start will change.
> >
> >
> > "Steve House [MVP]" wrote:
> >
> > > Using Project 2003 Pro with all service packs up to date. I just asked
> > > about task 11's predecessor, but then I tried it both ways - no
> predecessor
> > > for task 11 or Activity 3 FS to Task 11. Either way I get no change in
> the
> > > late start dates for any of the tasks whether they're indented under the
> > > summary or not. I followed your directions to the letter, re-check your
> > > message quoted below to make sure there's no typo that lead me someplace
> > > other than where you intended.
> > >
> > > There are no other tasks in the project. When you say indent under the
> > > summary, you are NOT indenting task 1 labeled "summary" but are
> indenting
> > > tasks 2 though 15, right?
> > >
> > > --
> > > Steve House [MVP]
> > > MS Project Trainer & Consultant
> > > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> > >
> > >
> > >
> > > "Sean" <Sean@discussions.microsoft.com> wrote in message
> > > news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> > > > Let me explain better.
> > > >
> > > > Create a project with the following info. The summary task is not
> Linked.
> > > > Don't indent it under the summary until you've added all the tasks.
> All
> > > > relationships are FS. Use a 5 day duration for all tasks. Insert the
> late
> > > > start field into your table.
> > > >
> > > > Now, indent all the tasks under the sumary task. Watch the late dates
> > > > change. They shouldn't becuase there is no link or relationship to
> the
> > > > summary line. Microsoft has acknowledged the problem but has made no
> > > > promise
> > > > to fix it. I've heard of some work around's but not found one that is
> > > > 100%
> > > >
> > > > Thanks
> > > > Sean
> > > >
> > > > ID NAME PRED
> > > > 1 summary
> > > > 2 Start Milestone #1
> > > > 3 Activity #1 2
> > > > 4 Activity #2 3
> > > > 5 Activity #3 4
> > > > 6 Finish Milestone #1 5,10
> > > > 7 Start Milestone #2
> > > > 8 Activity #4 7
> > > > 9 Activity #5 8
> > > > 10 Activity #6 9
> > > > 11 Start Milestone # 3
> > > > 12 Activity #7 11
> > > > 13 Activity #8 12
> > > > 14 Activity #9 13
> > > > 15 Finish Milestone #2 14
> > > >
> > > >
> > > >
> > > >
> > > > "Steve House [MVP]" wrote:
> > > >
> > > >> I'm not aware of any "bug" like you're describing. The total slack
> time
> > > >> of
> > > >> a task is the amount of time it could be delayed without delaying the
> > > >> project finish, in a nutshell. Imagine Summary Task A with subtasks
> A1
> > > >> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur
> in
> > > >> parallel, all starting the same day. Summary task A links to Summary
> X
> > > >> FS
> > > >> and Summary X in turn links FS to the Finish milestone. What are the
> > > >> late
> > > >> dates of A1, A2, & A3? Summary A's finish is determined by A3 so the
> > > >> late
> > > >> date of A3 and Summary A are the same. Only if Summary A is delayed
> past
> > > >> that point will Summary X be delayed, hence that is also the latest
> date
> > > >> it
> > > >> can finish without delaying the project's finish. The late finishes
> of
> > > >> A1
> > > >> and A2 are also that same date as A3 (which is also the late finish
> of
> > > >> Summary A), since they could slip by 2 or 1 day respectively before
> they
> > > >> delay the finish of Summary A. I think that is what you're
> describing in
> > > >> your posting but where's the bug in that? That is exactly the way
> late
> > > >> starts and late finishes are supposed to be calculated and that's the
> way
> > > >> project does calculate them. And this is even with linking between
> the
> > > >> summary tasks, which is often considered a bad idea. The alternative
> > > >> linking would have A1, A2, and A3 all as predecessors to X1 and no
> links
> > > >> directly in or out of the summary tasks themselves but the results
> are
> > > >> exactly the same.
> > > >>
> > > >> If I'm missing something here, please give us some concrete example
> that
> > > >> demonstrates what you consider to be this bug - what Project gives
> you
> > > >> and
> > > >> what you think it should be giving you instead (and why you feel
> Project
> > > >> is
> > > >> wrong and your way is right). I'm really curious.
> > > >> --
> > > >> Steve House [MVP]
> > > >> MS Project Trainer & Consultant
> > > >> Visit http://www.mvps.org/project/faqs.htm for the FAQs
> > > >>
> > > >>
> > > >>
> > > >>
> > > >>
> > > >> "Sean" <Sean@discussions.microsoft.com> wrote in message
> > > >> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> > > >> > Many of you know there is a "bug" in MS Project that affects the
> late
> > > >> > dates
> > > >> > and backward pass.
> > > >> >
> > > >> > If you indent a group of tasks under the summary task the late
> dates
> > > >> > for
> > > >> > that group are changed by the summary task. A weird problem that
> only
> > > >> > surfaces when calculating total slack and the backward pass.
> > > >> >
> > > >> > I've heard of some people using MSO/MFO anchors at the end of thier
> > > >> > network
> > > >> > to solve this. Does anybody else have a solution. My company (a
> > > >> > rather
> > > >> > large one) has submitted this to Microsoft and they acknowledge
> that it
> > > >> > is
> > > >> > a
> > > >> > bug, but aren't planning on fixing it anytime soon.
> > > >> >
> > > >> > Please advise.
> > > >> >
> > > >> > Sean
> > > >> >
> > > >>
> > > >>
> > >
> > >
>
>
>

Re: Late Dates incorrect after indenting under Summary Task by JackD

JackD
Tue Mar 01 11:06:36 CST 2005

It only occurs when you have a FNLT constraint so simply avoid using them. I
can't recall ever having to use one except when doing some analysis and even
then if you move it outside the summary it isn't a problem.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

.
"Sean" <Sean@discussions.microsoft.com> wrote in message
news:9E937293-69B6-49A1-BD7D-E842979D6DE1@microsoft.com...
> Microsoft hasn't given any recommendations, they are exploring the fix to
> thier "undesirable feature." If you don't use outlining it calcs
correctly.
> The other fix I've seen is to put a "ghost" node with a MSO after the end
of
> the last milestone and link it to the last FNLT. However, you have to do
> this for each path through your network. On a 10,000 line file you now
have
> 100 extra "ghost" milestones.
>
> Don't mean for you to spend a lot of time on this, was just curious of
> others encountered it and possibly had a workaround.
>
> Thanks
>
> "JackD" wrote:
>
> > Hm.
> > Another reason to avoid constraints.
> > Of course the workaround is to put the task with the finish constraint
> > outside the summary task. Is that what Microsoft advised you to do?
> >
> > --
> > -Jack ... For project information and macro examples visit
> > http://masamiki.com/project
> >
> > ..
> > "Sean" <Sean@discussions.microsoft.com> wrote in message
> > news:3AE2FAA1-12AE-421C-8B5E-D223D2605338@microsoft.com...
> > > Okay, Sorry for the confusion. Forgot the critical part of
constraints.
> > > Make a quick network with the project start date of 2/28/05.
> > >
> > > Name Dur Pred Constraint Type Constraint date
> > > Summary 1 day? ASAP NA
> > > Start Milestone One 0 days SNET 3/10/2005
> > > Task One 5 days 2 ASAP NA
> > > Task Two 5 days 3 ASAP NA
> > > Task Three 5 days 4 ASAP NA
> > > Task Four 5 days 5 ASAP NA
> > > Finish Milestone 0 days 6 FNLT 5/19/2005
> > >
> > > Insert the late start field. After you've entered in the network
> > highlight
> > > and indent everything under the summary task. The late start will
change.
> > >
> > >
> > > "Steve House [MVP]" wrote:
> > >
> > > > Using Project 2003 Pro with all service packs up to date. I just
asked
> > > > about task 11's predecessor, but then I tried it both ways - no
> > predecessor
> > > > for task 11 or Activity 3 FS to Task 11. Either way I get no change
in
> > the
> > > > late start dates for any of the tasks whether they're indented under
the
> > > > summary or not. I followed your directions to the letter, re-check
your
> > > > message quoted below to make sure there's no typo that lead me
someplace
> > > > other than where you intended.
> > > >
> > > > There are no other tasks in the project. When you say indent under
the
> > > > summary, you are NOT indenting task 1 labeled "summary" but are
> > indenting
> > > > tasks 2 though 15, right?
> > > >
> > > > --
> > > > Steve House [MVP]
> > > > MS Project Trainer & Consultant
> > > > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> > > >
> > > >
> > > >
> > > > "Sean" <Sean@discussions.microsoft.com> wrote in message
> > > > news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> > > > > Let me explain better.
> > > > >
> > > > > Create a project with the following info. The summary task is not
> > Linked.
> > > > > Don't indent it under the summary until you've added all the
tasks.
> > All
> > > > > relationships are FS. Use a 5 day duration for all tasks. Insert
the
> > late
> > > > > start field into your table.
> > > > >
> > > > > Now, indent all the tasks under the sumary task. Watch the late
dates
> > > > > change. They shouldn't becuase there is no link or relationship
to
> > the
> > > > > summary line. Microsoft has acknowledged the problem but has made
no
> > > > > promise
> > > > > to fix it. I've heard of some work around's but not found one
that is
> > > > > 100%
> > > > >
> > > > > Thanks
> > > > > Sean
> > > > >
> > > > > ID NAME PRED
> > > > > 1 summary
> > > > > 2 Start Milestone #1
> > > > > 3 Activity #1 2
> > > > > 4 Activity #2 3
> > > > > 5 Activity #3 4
> > > > > 6 Finish Milestone #1 5,10
> > > > > 7 Start Milestone #2
> > > > > 8 Activity #4 7
> > > > > 9 Activity #5 8
> > > > > 10 Activity #6 9
> > > > > 11 Start Milestone # 3
> > > > > 12 Activity #7 11
> > > > > 13 Activity #8 12
> > > > > 14 Activity #9 13
> > > > > 15 Finish Milestone #2 14
> > > > >
> > > > >
> > > > >
> > > > >
> > > > > "Steve House [MVP]" wrote:
> > > > >
> > > > >> I'm not aware of any "bug" like you're describing. The total
slack
> > time
> > > > >> of
> > > > >> a task is the amount of time it could be delayed without delaying
the
> > > > >> project finish, in a nutshell. Imagine Summary Task A with
subtasks
> > A1
> > > > >> (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they
occur
> > in
> > > > >> parallel, all starting the same day. Summary task A links to
Summary
> > X
> > > > >> FS
> > > > >> and Summary X in turn links FS to the Finish milestone. What are
the
> > > > >> late
> > > > >> dates of A1, A2, & A3? Summary A's finish is determined by A3 so
the
> > > > >> late
> > > > >> date of A3 and Summary A are the same. Only if Summary A is
delayed
> > past
> > > > >> that point will Summary X be delayed, hence that is also the
latest
> > date
> > > > >> it
> > > > >> can finish without delaying the project's finish. The late
finishes
> > of
> > > > >> A1
> > > > >> and A2 are also that same date as A3 (which is also the late
finish
> > of
> > > > >> Summary A), since they could slip by 2 or 1 day respectively
before
> > they
> > > > >> delay the finish of Summary A. I think that is what you're
> > describing in
> > > > >> your posting but where's the bug in that? That is exactly the
way
> > late
> > > > >> starts and late finishes are supposed to be calculated and that's
the
> > way
> > > > >> project does calculate them. And this is even with linking
between
> > the
> > > > >> summary tasks, which is often considered a bad idea. The
alternative
> > > > >> linking would have A1, A2, and A3 all as predecessors to X1 and
no
> > links
> > > > >> directly in or out of the summary tasks themselves but the
results
> > are
> > > > >> exactly the same.
> > > > >>
> > > > >> If I'm missing something here, please give us some concrete
example
> > that
> > > > >> demonstrates what you consider to be this bug - what Project
gives
> > you
> > > > >> and
> > > > >> what you think it should be giving you instead (and why you feel
> > Project
> > > > >> is
> > > > >> wrong and your way is right). I'm really curious.
> > > > >> --
> > > > >> Steve House [MVP]
> > > > >> MS Project Trainer & Consultant
> > > > >> Visit http://www.mvps.org/project/faqs.htm for the FAQs
> > > > >>
> > > > >>
> > > > >>
> > > > >>
> > > > >>
> > > > >> "Sean" <Sean@discussions.microsoft.com> wrote in message
> > > > >> news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> > > > >> > Many of you know there is a "bug" in MS Project that affects
the
> > late
> > > > >> > dates
> > > > >> > and backward pass.
> > > > >> >
> > > > >> > If you indent a group of tasks under the summary task the late
> > dates
> > > > >> > for
> > > > >> > that group are changed by the summary task. A weird problem
that
> > only
> > > > >> > surfaces when calculating total slack and the backward pass.
> > > > >> >
> > > > >> > I've heard of some people using MSO/MFO anchors at the end of
thier
> > > > >> > network
> > > > >> > to solve this. Does anybody else have a solution. My company
(a
> > > > >> > rather
> > > > >> > large one) has submitted this to Microsoft and they acknowledge
> > that it
> > > > >> > is
> > > > >> > a
> > > > >> > bug, but aren't planning on fixing it anytime soon.
> > > > >> >
> > > > >> > Please advise.
> > > > >> >
> >