JulieS
Wed Aug 27 08:46:44 CDT 2008
Hello hugh,
Double click on the resource name and on the Cost tab of the Resource
Information dialog, supply effective dates and new rates.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project