Jack
Wed Mar 12 11:53:54 CDT 2008
Another possibility:
You have a link to the summary task for that task, and the predecessor to
that summary task is completing in two weeks.
-Jack Dahlgren
"Jan De Messemaeker" <janremovethis@prom-ade.be> wrote in message
news:eZY2DwBhIHA.6032@TK2MSFTNGP03.phx.gbl...
> Hi,
>
> - The task has a resource assigned that is not available OR
> - You have Resource Leveling put to automatic and the resoruce on the task
> was overallocated OR
> - The task has a task calendar assigned to it, and the calendar has
> nonworking time
>
> Hope this helps,
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
>
http://users.online.be/prom-ade/Calendar.pdf
> "Kay" <kay_schulz@yahoo.com> wrote in message
> news:fd767373-9ba0-45f7-9846-de5c3a77468e@n77g2000hse.googlegroups.com...
>> Hi
>> I found something very strange
>> I have a task which is fixed work.
>> The constraint is asap
>> I use a predecessor so I want that my task starts
>> directly after the predecessor.
>> But it does not
>> It starts two weeks later.
>> Why?
>> I have all tasks on asap all group tasks I checked about constraints
>> etc. but I do not find the solution to this problem.
>> Help please.
>> Kay
>
>