JulieS
Wed Sep 10 16:33:46 CDT 2008
You're welcome badjuju. Glad to have helped and thanks for the
feedback.
Julie
"badjuju" <badjuju@discussions.microsoft.com> wrote in message
news:9A06774A-ACA5-410F-9AE8-EAB92975AA0C@microsoft.com...
> Thanks a million JulieS! That answer did the trick
>
> "JulieS" wrote:
>
>> Hi,
>>
>> Right click the Task Name column. From the shortcut menu, choose
>> Insert Column. In the list, select Indicator and click OK.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit
http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>> "badjuju" <badjuju@discussions.microsoft.com> wrote in message
>> news:0D09A82E-ED73-440F-A00D-5994C2053520@microsoft.com...
>> >I have hidden the Indicator Column (with the blue circle & white
>> >"i".. top
>> > left between Number column and Task Name Column) in Project
>> > 2007.
>> > Now can't
>> > 'un-hide' it. I have searched the General Questions and did not
>> > find
>> > anything. It should be easy... I have tried selecting all
>> > Project
>> > columns
>> > (From the Field Number Column to the Finish Column) to see if i
>> > could unhide
>> > it. Didn't work. I also looked for a long time in the menu bar
>> > and
>> > did not
>> > find anything.
>> > I am sure that this is very easy, however I am unable to find
>> > the
>> > answer or
>> > method to accomplish.
>> > Thanks
>>
>>
>>