Mike
Sat May 17 14:37:21 CDT 2008
Hi Akm,
Welcome to this Microsoft Project newsgroup :)
If you build your project with logical links between tasks, they cannot
overlap unless you dictate some lead time. However, when you have assigned
resources, then Project will show you any overlap of resources and will
allow you to select levelling to remove those overlaps.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for my Project Tutorials
akm wrote:
> Will Project2007 show notification of where/which tasks over-lap by
> highlighting the task list, or by some other obvious means other than
> having to search through the gantt chart ?