JulieS
Thu Jun 08 14:01:32 CDT 2006
Hi srs67,
In order to generate earned value data in Project you will need:
Tasks
Resources with Standard Rates and Overtime Rates (if you intend to
assign OT)
Resources assigned to the Tasks
Baseline
Tracking Data (Actual Work, Remaining Work, etc)
I hope this helps. Let us know how you get along.
Julie
<srs76@cox.net> wrote in message
news:1149793043.588397.62530@g10g2000cwb.googlegroups.com...
> Thank you, that was informative, but I'm looking for info as to how to
> feed MS Project information necessary to create a EVM table i.e. -
> resouces, budget, etc.
> Ratheesh wrote:
>> Use this link
>>
http://www.esi-intl.com/public/webseminar/20060413evm.asp and
>> click on the "View Archive" button on right side.
>>
>> This may ask you to install Microsoft Live application and may be to
>> create
>> a new account etc.
>>
>> Hope this helps.If you need more info please post
>>
>> "srs76@cox.net" wrote:
>>
>> > I'm trying to calculate EV in a WBS project plan that I've already
>> > completed.
>> > Do I have to save my baseline in order for the EVM table to
>> > calculate???
>> > I've bought 3 books and no where does it give you a step by step
>> > breakdown of how to actually make the EV table work.
>> >
>> > Can someone offer a step by step take on how I should approach this
>> > or
>> > a website or publication in which I can get a better understanding.
>> >
>> >
>> > Ms. Conquest - Dept. Homeland Security
>> >
>> >
>