CB
Thu May 08 15:46:04 CDT 2008
Thanks Jack. This was exactly what I thought. I don't favor using these as
I don't have control over them. I prefer to enter the effort into the task
usage for LOE tasks. However, sometimes we can't get around a
customer/client request to show milestones at the top of the schedule and
this really doesn't fit the flow of a schedule. I will recommend that we use
these only to mirror start, finish and % completes for milestones that need
to be displayed at the beginning.
"Jack Dahlgren" wrote:
> The name of the link - "!Link_n" is just the way links are identified. They
> are numbered sequentially in the order that they are created.
>
> You can't really follow the link back to the source. You can only follow it
> back to the document that it links to.
> Those sorts of link are quite fragile and date back to the early versions of
> Project. I'd be very careful about using them as they have a reputation for
> being easy to break and difficult to troubleshoot. The only way to work with
> them is through the "Edit Menu" / "Links" dialog.
>
> -Jack Dahlgren
>
>
> "CB" <CB@dsucussions.microsoft.com> wrote in message
> news:C024F1D8-213B-41AD-9037-B068A23B4160@microsoft.com...
> > Hi Mike,
> > Thanks for your response. I know how to set up the hammock tasks. My
> > qestion is related in to how to follow the link back to the source data
> > and
> > what the !Link means in the linked data path.
> > Any info would be appreciated.
> >
> >
> > "Mike Glen" wrote:
> >
> >> Hi CB,
> >>
> >> Welcome to this Microsoft Project newsgroup :-)
> >>
> >> The simplest way to set up a hammock task is indicated in FAQ Item: 19.
> >> Hammock Tasks.
> >>
> >> FAQs, companion products and other useful Project information can be seen
> >> at
> >> this web address:
http://project.mvps.org/faqs.htm
> >>
> >> Hope this helps - please let us know how you get on :-)
> >>
> >> Mike Glen
> >> Project MVP
> >>
> >> CB wrote:
> >> > I am using a hammock task to pull information from a task to the top
> >> > of the schedule to satisfy some requirement. My question is when I
> >> > select the cell and go to edit/Link change source the following is
> >> > displayed: Path\filename.mpp!LINK_4. My question is what does
> >> > !LINK_4 mean? I inserted another hammock and dynamically linked it
> >> > and it displays the same thing with !LINK_6 on the end.
> >> > Any ideas? I am using MSOP 2007.
> >> > Thanks in advance for your comments/insight.
> >>
> >>
> >>
>
>
>