Dale
Tue Feb 07 18:01:50 CST 2006
Max --
In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
no, there is no way to do this. I believe the best you can do is to save it
as an .mpp file, delete it from the Project Server database, and then import
it using Tools - Enterprise Options - Import Project to Enterprise. Hope
this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Max" <Max@discussions.microsoft.com> wrote in message
news:3DA0A8A2-CC50-4184-AA4E-270F25807335@microsoft.com...
> Is there a way to change a project from 'administrative' back to a normal
> project? The checkbox is checked indicating the project is
> administrative,
> when in fact it is not supposed to be. The checkbox is greyed out, so
> even
> if I do a 'Save' I am unable to change it. Any help would be appreciated.