When assigning resource to task in the Resource Work view, the drop down
resource list appears in Resource ID order. Is there a way for the drop down
list to show Resource Name order?

MSPLearner

Re: Forn View - Resource Work by JulieS

JulieS
Sat Jul 22 19:40:49 CDT 2006

Hi MSPLearner,

Yes, you can. If you sort the Resource Sheet (Project > Sort > Sort by)
and select the option for Permanently renumber resources, the drop down
list will display with the new sort order.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

"MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
news:B43D3BD9-86C7-48F3-ADBB-E511F84DEEE0@microsoft.com...
> When assigning resource to task in the Resource Work view, the drop
> down
> resource list appears in Resource ID order. Is there a way for the
> drop down
> list to show Resource Name order?
>
> MSPLearner



Re: Forn View - Resource Work by MSPLearner

MSPLearner
Sun Jul 23 14:04:01 CDT 2006

Wow, thank you. I learnt something new.

MSPLearner

"JulieS" wrote:

> Hi MSPLearner,
>
> Yes, you can. If you sort the Resource Sheet (Project > Sort > Sort by)
> and select the option for Permanently renumber resources, the drop down
> list will display with the new sort order.
>
> --
> I hope this helps. Let us know how you get along.
>
> Julie
>
> Visit http://project.mvps.org/ for FAQs and more information about
> Microsoft Project.
>
> "MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
> news:B43D3BD9-86C7-48F3-ADBB-E511F84DEEE0@microsoft.com...
> > When assigning resource to task in the Resource Work view, the drop
> > down
> > resource list appears in Resource ID order. Is there a way for the
> > drop down
> > list to show Resource Name order?
> >
> > MSPLearner
>
>
>

Re: Forn View - Resource Work by JulieS

JulieS
Sun Jul 23 14:11:32 CDT 2006

You're very welcome and thanks for the feedback.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

"MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
news:6432B959-660F-47A2-9138-868C89BC01B6@microsoft.com...
> Wow, thank you. I learnt something new.
>
> MSPLearner
>
> "JulieS" wrote:
>
>> Hi MSPLearner,
>>
>> Yes, you can. If you sort the Resource Sheet (Project > Sort > Sort
>> by)
>> and select the option for Permanently renumber resources, the drop
>> down
>> list will display with the new sort order.
>>
>> --
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>>
>> Visit http://project.mvps.org/ for FAQs and more information about
>> Microsoft Project.
>>
>> "MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
>> news:B43D3BD9-86C7-48F3-ADBB-E511F84DEEE0@microsoft.com...
>> > When assigning resource to task in the Resource Work view, the drop
>> > down
>> > resource list appears in Resource ID order. Is there a way for the
>> > drop down
>> > list to show Resource Name order?
>> >
>> > MSPLearner
>>
>>
>>



Re: Forn View - Resource Work by MSPLearner

MSPLearner
Sun Jul 23 14:13:02 CDT 2006

One more question. I am using a resource pool file. So before I sort and
permanently renumber resources, I should open all the sharer files, right?

MSPLearner

"JulieS" wrote:

> Hi MSPLearner,
>
> Yes, you can. If you sort the Resource Sheet (Project > Sort > Sort by)
> and select the option for Permanently renumber resources, the drop down
> list will display with the new sort order.
>
> --
> I hope this helps. Let us know how you get along.
>
> Julie
>
> Visit http://project.mvps.org/ for FAQs and more information about
> Microsoft Project.
>
> "MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
> news:B43D3BD9-86C7-48F3-ADBB-E511F84DEEE0@microsoft.com...
> > When assigning resource to task in the Resource Work view, the drop
> > down
> > resource list appears in Resource ID order. Is there a way for the
> > drop down
> > list to show Resource Name order?
> >
> > MSPLearner
>
>
>

Re: Forn View - Resource Work by JulieS

JulieS
Sun Jul 23 15:21:01 CDT 2006

Hi MSPLearner,

Yes, I would recommend opening all files read/write perform the sort,
then save and close.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
"MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
news:6D9496FE-A825-47DD-8041-6E261E12AEFD@microsoft.com...
> One more question. I am using a resource pool file. So before I sort
> and
> permanently renumber resources, I should open all the sharer files,
> right?
>
> MSPLearner
>
> "JulieS" wrote:
>
>> Hi MSPLearner,
>>
>> Yes, you can. If you sort the Resource Sheet (Project > Sort > Sort
>> by)
>> and select the option for Permanently renumber resources, the drop
>> down
>> list will display with the new sort order.
>>
>> --
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>>
>> Visit http://project.mvps.org/ for FAQs and more information about
>> Microsoft Project.
>>
>> "MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
>> news:B43D3BD9-86C7-48F3-ADBB-E511F84DEEE0@microsoft.com...
>> > When assigning resource to task in the Resource Work view, the drop
>> > down
>> > resource list appears in Resource ID order. Is there a way for the
>> > drop down
>> > list to show Resource Name order?
>> >
>> > MSPLearner
>>
>>
>>