I would like to create a filter that identified slipping tasks for an interim
plan. My understanding of the Slipping Tasks filter is that it is based on
the original Baseline. Thanks in advance for your time on this matter.

Re: Filtering Slipping Tasks with an Interim Plan by JulieS

JulieS
Thu Jun 14 06:41:06 CDT 2007

Hello,

The Slipping Tasks filter tests for tasks that have not been completed
have a baseline saved and a Finish later than baseline finish.

If you have saved alternate baselines, I suggest making a copy of the
existing filter, give the filter a new name and change the references to
Baseline Finish to the other baseline. For example, if you have saved
Baseline5 the filter would read:

Actual Finish equals NA
AND
Baseline5 Finish does not equal NA
AND
Finish is greater than [Baseline5 Finish]

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"GDCross" <GDCross@discussions.microsoft.com> wrote in message
news:265065B9-F6AB-4B6F-83FF-9B65C38F3688@microsoft.com...
>I would like to create a filter that identified slipping tasks for an
>interim
> plan. My understanding of the Slipping Tasks filter is that it is
> based on
> the original Baseline. Thanks in advance for your time on this matter.