Hi,

I have ms project 2003; I entered all the planned expenses of the team, but
at the end of the week I know exaclty how much was expensed, how can I enter
this new information and then compare planned expenses vs real expensed?

Re: Expenses - Planned vs real by Dave

Dave
Thu May 08 02:25:09 CDT 2008

toto2000ff wrote:
> Hi,
>
> I have ms project 2003; I entered all the planned expenses of the team, but
> at the end of the week I know exaclty how much was expensed, how can I enter
> this new information and then compare planned expenses vs real expensed?
>

Baseline them? You don't say whether you have separate expense
activities or whether they are included in the costs of individual
activities. However