I recently imported a select number of resources from a project into the
enterprise resource pool. This action made the balance of my resource
non-viewable as enterprise resources - even when startin a new blank project
I could not see my users using Build team from server. To UNDO the situation
I used the Clean Up Project server.. and deleted the imported resources.
This did not solve the problem. I still see no resources from PWS when I
attempt to build team from PS.
I wonder if this has anything to do with the fact I have a default set to
administrator for Project server when I launch Project Office 2003. Does this
affect the view to the enterprise? I don't see how but thought I would ask.
Note: I am a user in PWS with administrator rights. I needed to set the
project server accounts to Administrator in order to edit the global template.
All I really want to do is get back to the state I was in prior to the
Import of enterprise resources. There are only 15 users in PWS and it is not
currently in use. What do you suggest I do?