I created a task that has a duration of 8 hours (10 hous or work) and in the Gantt Chart view, the blue bar for that task starts on a Thursday with 1 hour of work, and then has .................. with it resuming on Tuesday. What does that mean and why did it do that?

Thanks!

Jeremy

Re: Easy Question: Gantt bar split by . . . by Mike

Mike
Fri Jul 02 09:53:09 CDT 2004

Hi Jeremy,

Is this the only task? Have you assigned resources? Have you changed any
working hour calendars? More info please.

Mike Glen
MS Project MVP


"JeremyE" <JeremyE@discussions.microsoft.com> wrote in message
news:EE5569A7-1E87-421C-900C-480AAD1E6A13@microsoft.com...
> I created a task that has a duration of 8 hours (10 hous or work) and in
the Gantt Chart view, the blue bar for that task starts on a Thursday with 1
hour of work, and then has .................. with it resuming on Tuesday.
What does that mean and why did it do that?
>
> Thanks!
>
> Jeremy



Re: Easy Question: Gantt bar split by . . . by JeremyE

JeremyE
Fri Jul 02 10:21:02 CDT 2004

No, there are about 30 tasks, with two resources (programmers). I changed the working calendar (1 day = 4.8 hours) and I changed the default working day to be from 12:12 pm to 5 pm to force the 4.8 hour day. Let me know if you need more info, but this is the only task doing it. If you want, I can email screen shots or whatever you would like.
Thanks!

Jeremy

"Mike Glen" wrote:

> Hi Jeremy,
>
> Is this the only task? Have you assigned resources? Have you changed any
> working hour calendars? More info please.
>
> Mike Glen
> MS Project MVP
>
>
> "JeremyE" <JeremyE@discussions.microsoft.com> wrote in message
> news:EE5569A7-1E87-421C-900C-480AAD1E6A13@microsoft.com...
> > I created a task that has a duration of 8 hours (10 hous or work) and in
> the Gantt Chart view, the blue bar for that task starts on a Thursday with 1
> hour of work, and then has .................. with it resuming on Tuesday.
> What does that mean and why did it do that?
> >
> > Thanks!
> >
> > Jeremy
>
>
>

Re: Easy Question: Gantt bar split by . . . by Mike

Mike
Fri Jul 02 15:41:55 CDT 2004

Hi Jeremy. Better to send me the project - zip it up and email it to me.


Mike Glen
Project MVP


"JeremyE" <JeremyE@discussions.microsoft.com> wrote in message
news:F92A3630-5B99-4FE5-B963-7F2D7067E1AF@microsoft.com...
> No, there are about 30 tasks, with two resources (programmers). I changed
the working calendar (1 day = 4.8 hours) and I changed the default working
day to be from 12:12 pm to 5 pm to force the 4.8 hour day. Let me know if
you need more info, but this is the only task doing it. If you want, I can
email screen shots or whatever you would like.
> Thanks!
>
> Jeremy
>
> "Mike Glen" wrote:
>
> > Hi Jeremy,
> >
> > Is this the only task? Have you assigned resources? Have you changed
any
> > working hour calendars? More info please.
> >
> > Mike Glen
> > MS Project MVP
> >
> >
> > "JeremyE" <JeremyE@discussions.microsoft.com> wrote in message
> > news:EE5569A7-1E87-421C-900C-480AAD1E6A13@microsoft.com...
> > > I created a task that has a duration of 8 hours (10 hous or work) and
in
> > the Gantt Chart view, the blue bar for that task starts on a Thursday
with 1
> > hour of work, and then has .................. with it resuming on
Tuesday.
> > What does that mean and why did it do that?
> > >
> > > Thanks!
> > >
> > > Jeremy
> >
> >
> >



Re: Easy Question: Gantt bar split by . . . by Mike

Mike
Fri Jul 02 15:47:54 CDT 2004

Hi Jeremy. Better to send me the project - zip it up and email it to me.


Mike Glen
Project MVP


"JeremyE" <JeremyE@discussions.microsoft.com> wrote in message
news:F92A3630-5B99-4FE5-B963-7F2D7067E1AF@microsoft.com...
> No, there are about 30 tasks, with two resources (programmers). I changed
the working calendar (1 day = 4.8 hours) and I changed the default working
day to be from 12:12 pm to 5 pm to force the 4.8 hour day. Let me know if
you need more info, but this is the only task doing it. If you want, I can
email screen shots or whatever you would like.
> Thanks!
>
> Jeremy
>
> "Mike Glen" wrote:
>
> > Hi Jeremy,
> >
> > Is this the only task? Have you assigned resources? Have you changed
any
> > working hour calendars? More info please.
> >
> > Mike Glen
> > MS Project MVP
> >
> >
> > "JeremyE" <JeremyE@discussions.microsoft.com> wrote in message
> > news:EE5569A7-1E87-421C-900C-480AAD1E6A13@microsoft.com...
> > > I created a task that has a duration of 8 hours (10 hous or work) and
in
> > the Gantt Chart view, the blue bar for that task starts on a Thursday
with 1
> > hour of work, and then has .................. with it resuming on
Tuesday.
> > What does that mean and why did it do that?
> > >
> > > Thanks!
> > >
> > > Jeremy
> >
> >
> >