Re: Earned Value by BradWhitford
BradWhitford
Mon Jul 03 18:48:02 CDT 2006
Andrew, thank you very much for your help, you were right. The task's earned
value method was physical % complete. I'm not sure where you live, but I owe
you a beer. Thanks again.
--
Brad Whitford
"Andrew Lavinsky" wrote:
> Let me correct myself:
>
> Add the Earned Value Method field to your Gantt chart and see how each task
> is calculated. If indeed it is Physical % Complete, change to % Complete.
>
> Toggling in the Options menu only affects new tasks.
>
> Sorry about that.
>
> -A
>
> > Another angle: didn't see it covered in your post, but do you have MPP
> > set to calculate based on "% Complete" or "Physical % Complete."
> >
> > The latter would be consistent w/ the issue you seem to be having
> > (although am not sure if 2002 has that function - I guess it probably
> > does).
> >
> Tools>> Options > Calculation > Earned Value
> Tools>>
> > If it is Physical % Complete, see if toggling back to % Complete
> > doesn't resolve the issue.
> >
> > -A
> >
> >> All my costs are fixed costs as we use fixed price sub-contracts for
> >> the majority of our work. I currently have about 200 jobs
> >> progressing to some degree and there is only one that isn't
> >> progressing in BCWP. The total value is reducing as the work is
> >> progressing, but no BCWP value. My version of MSP is 2002.
> >>
> >> "Rod Gill" wrote:
> >>
> >>> When you assigned cost, was the cost for one or more Resources with
> >>> a $ rate or fixed cost. If fixed cost how is it accrued on the task?
> >>>
> >>> I've just checked and in 2003 BCWP is calculated as I would expect:
> >>> 50% progress and BCWP=50% of budgeted cost.
> >>>
> >>> --
> >>>
> >>> Rod Gill
> >>> Project MVP
> >>> Visit www.msproject-systems.com for Project Companion Tools and more
> >>> "Brad Whitford" <BradWhitford@discussions.microsoft.com> wrote in
> >>> message news:F9420160-DF71-468C-B881-46151A74C35B@microsoft.com...
> >>>> I am having a problem with one job in my current project. I have
> >>>> updated
> >>>> the
> >>>> %'s however in one job the BCWP has not progressed. I reset the
> >>>> %'s
> >>>> to
> >>>> zero,
> >>>> removed the $ values and then re-entered them, re-baselined, and
> >>>> then put
> >>>> the
> >>>> correct %'s back in. The BCWP field still did not populate. Can
> >>>> somebody
> >>>> please help. Thanks. (New user to this newsgroup)
> >>>> --
> >>>> Brad Whitford
>
>
>