davegb
Tue Jan 22 09:03:53 CST 2008
On Jan 19, 6:36=A0am, "Steve House" <sjhouse at hotmail dot com> wrote:
> Remember non-working time enters into the picture. =A0Imagine 2 2-day task=
s
> starting on Wednesday - their bars will cover Wed and Thur. =A0Now I link =
them
> FS. =A0Task 1's bar will cover Wed and Thur, Task 2's bar will cover Fri, =
Sat,
> Sun, Mon. =A0While the elpased time from start to finish for task 2 has
> increased from 2 days to 4, its duration has not actually changed and
> remains at 2 days, Sat and Sun not counting in the duration numbers becaus=
e
> they're non-working days. =A0I'll bet something like that is what you're
> seeing in your project. =A0You can't count on the total length of the Gant=
t
> bars as representing the duration and only the duration.
>
> --
> Steve House [Project MVP]
> MS Project Trainer & Consultant
> Visit
http://project.mvps.org/faqs.htmfor the FAQs
>
Good call, Steve!
> "Andre Bal" <Andre...@discussions.microsoft.com> wrote in message
>
> news:E209C216-8750-4159-83AE-821F61FFD83F@microsoft.com...
>
>
>
> > Problem is that the same task has a different duration in the bar when i=
t
> > is
> > unlinked, or linked.
>
> > Obvoiusly I understaand doing things paralell shortens duration. I an ju=
st
> > talking about 1 single task here that increases in duration when it is
> > given
> > a predecessor.
>
> > Andre
>
> > "davegb" wrote:
>
> >> On Jan 18, 2:36 am, Andre Bal <Andre B...@discussions.microsoft.com>
> >> wrote:
> >> > I have a bloking issue with a project file. IT is a detailed plan wit=
h
> >> > many
> >> > tasks that take between 5-15 minutes duration. After analising my
> >> > project, i
> >> > found that although several tasks take 5 minutes (listed in task
> >> > information), the gant chart bar displays about 1 hour.
>
> >> > Even stranger, if i remove the deprendency of such task, then the tas=
k
> >> > duration is still five minutes, however the bar will also change to 5=
> >> > minutes.
>
> >> > What is the cause of this ?
>
> >> > I have found no clues whatsowever, and my project duration is not
> >> > reliable
> >> > now.
>
> >> > All taks have fixed duration, effort drivven with NO resources used.
>
> >> > Please advise since my total leadtime is negatively affected (im am
> >> > running
> >> > a large disaster recovery test that MUST be fitted within a weekend, =
so
> >> > durastion releability is Key.
>
> >> When the tasks are linked, the project takes longer than when all the
> >> tasks are being done at the same time. A bunch of 5 min tasks,
> >> unlinked, no matter how many there are, take 5 min. If you have 12 5
> >> min tasks, and they are linked, they take 60 min.
>
> >> Hope this helps in your world.- Hide quoted text -
>
> - Show quoted text -