I have a Fixed Work task that will take 100 hours of Work. The resource is a
piece of equipment that is allocated at 100% Units on the 24 Hours Base
Calendar.

The Duration, however, is calculated at 12.5 days in the Task view, which is
what you'd expect for the Standard Base Calendar (8 hours/day). The Duration
should be just over 4 days for this resource at 24 hours/day, which is how it
appears in the Gantt chart (blue bar extends over a four day period).

What could be causing this? Thanks.


--

-Mike

Re: Duration Not Right When For a 24-hour Resource by Jan

Jan
Fri Mar 14 15:54:01 CDT 2008

Hi,

Days as a unit of time are not calculated through a calendar, nor are they
the difference between start and finish in true "days".
Days are the number of duration hours divided by what you find in Tools,
Option, Calendar, Hours per day. Full Stop. No link to any working time
calendar whatsoever.

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Mike" <Mike@discussions.microsoft.com> wrote in message
news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
>I have a Fixed Work task that will take 100 hours of Work. The resource is
>a
> piece of equipment that is allocated at 100% Units on the 24 Hours Base
> Calendar.
>
> The Duration, however, is calculated at 12.5 days in the Task view, which
> is
> what you'd expect for the Standard Base Calendar (8 hours/day). The
> Duration
> should be just over 4 days for this resource at 24 hours/day, which is how
> it
> appears in the Gantt chart (blue bar extends over a four day period).
>
> What could be causing this? Thanks.
>
>
> --
>
> -Mike



Re: Duration Not Right When For a 24-hour Resource by Mike

Mike
Fri Mar 14 15:59:19 CDT 2008

Hi Mike,

Welcome to this Microsoft Project newsgroup :)

If all your work is on a 24 hour basis then you should change the working
hours: see FAQ Item: 5. Default Working Hours. However, I suspect this is a
one-off and Project cannot handle effectively different calendars - it has
to pick one to show - the standard project calendar based on an 8-hour day
as you discovered. Don't forget that although the Duration shows 12.5 days,
the Work is correct at 100 hours. You'll have to live with that.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials



"Mike" <Mike@discussions.microsoft.com> wrote in message
news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
>I have a Fixed Work task that will take 100 hours of Work. The resource is
>a
> piece of equipment that is allocated at 100% Units on the 24 Hours Base
> Calendar.
>
> The Duration, however, is calculated at 12.5 days in the Task view, which
> is
> what you'd expect for the Standard Base Calendar (8 hours/day). The
> Duration
> should be just over 4 days for this resource at 24 hours/day, which is how
> it
> appears in the Gantt chart (blue bar extends over a four day period).
>
> What could be causing this? Thanks.
>
>
> --
>
> -Mike



Re: Duration Not Right When For a 24-hour Resource by Mike

Mike
Mon Mar 17 11:16:03 CDT 2008

Thanks for your reply, Jan.

I'm baffled by the purpose of having the 24-hour calendar if it's not used.
Why have it?

--

-Mike


"Jan De Messemaeker" wrote:

> Hi,
>
> Days as a unit of time are not calculated through a calendar, nor are they
> the difference between start and finish in true "days".
> Days are the number of duration hours divided by what you find in Tools,
> Option, Calendar, Hours per day. Full Stop. No link to any working time
> calendar whatsoever.
>
> Hope this helps,
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Mike" <Mike@discussions.microsoft.com> wrote in message
> news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
> >I have a Fixed Work task that will take 100 hours of Work. The resource is
> >a
> > piece of equipment that is allocated at 100% Units on the 24 Hours Base
> > Calendar.
> >
> > The Duration, however, is calculated at 12.5 days in the Task view, which
> > is
> > what you'd expect for the Standard Base Calendar (8 hours/day). The
> > Duration
> > should be just over 4 days for this resource at 24 hours/day, which is how
> > it
> > appears in the Gantt chart (blue bar extends over a four day period).
> >
> > What could be causing this? Thanks.
> >
> >
> > --
> >
> > -Mike
>
>
>

Re: Duration Not Right When For a 24-hour Resource by Mike

Mike
Mon Mar 17 11:29:00 CDT 2008

Thanks for replying, Glen.

We have a mix of resources where some of our equipment is run over a 24 hour
period, but the people and other equipment will be utilized within the
standard 8 hours workday.

If project can't handle the use of multiple calendars, then why does it know
that the duration is 4 days when displaying the Gantt chart bars? Project's
inability to handle multiple calendars comes as a shock and disappointment in
what I would consider a pretty common scenario.

Approaching the problem another way, if the calendar options were set so
that "Hours per day" were 24 hours rather than the default 8 hours, would
Project schedule tasks properly since working time of the 8-hour-per-day
resources were restricted by their Standard calendars?

--

-Mike


"Mike Glen" wrote:

> Hi Mike,
>
> Welcome to this Microsoft Project newsgroup :)
>
> If all your work is on a 24 hour basis then you should change the working
> hours: see FAQ Item: 5. Default Working Hours. However, I suspect this is a
> one-off and Project cannot handle effectively different calendars - it has
> to pick one to show - the standard project calendar based on an 8-hour day
> as you discovered. Don't forget that although the Duration shows 12.5 days,
> the Work is correct at 100 hours. You'll have to live with that.
>
> FAQs, companion products and other useful Project information can be seen at
> this web address: http://project.mvps.org/faqs.htm
> Hope this helps - please let us know how you get on :)
>
> Mike Glen
> MS Project MVP
> See http://tinyurl.com/2xbhc for Project Tutorials
>
>
>
> "Mike" <Mike@discussions.microsoft.com> wrote in message
> news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
> >I have a Fixed Work task that will take 100 hours of Work. The resource is
> >a
> > piece of equipment that is allocated at 100% Units on the 24 Hours Base
> > Calendar.
> >
> > The Duration, however, is calculated at 12.5 days in the Task view, which
> > is
> > what you'd expect for the Standard Base Calendar (8 hours/day). The
> > Duration
> > should be just over 4 days for this resource at 24 hours/day, which is how
> > it
> > appears in the Gantt chart (blue bar extends over a four day period).
> >
> > What could be causing this? Thanks.
> >
> >
> > --
> >
> > -Mike
>
>
>

Re: Duration Not Right When For a 24-hour Resource by Steve

Steve
Mon Mar 17 12:55:13 CDT 2008

It's not that Project can't use multiple calendars - it does so very nicely.
The confusion arises when one forgets that duration is ALWAYS actually
measured and calculated in units of working time minutes to the nearest
10th. In order to use more convenient units of days, weeks, months, etc,
they have to be converted to and from minutes. The conversion factors
applied are global within a project and independent of the working time
calendar. With the default hours per day setting of 8
(Tools/Options/Calendar) ANY time period of 480 minutes is considered a
"day." The calendars, OTOH, determine WHICH minutes out of the 24-hour
sunrise to sunrise day are to be considered working time. We enter a task
with a duration of 3 days, ie, 1440 working time minutes, starting Monday @
8am. If the calendar governing that task is the standard 8-hour default
calendar, those 3 480-minute "days" run 0800-1700 Mon, 0800-1700 Tue, and
0800-1700 Wed. On the other hand, if the 24-hour calendar is governing that
task, those same 3 480-minute "days" run 0800-1600 Mon, 1600 Mon-0000 Tue,
0000-0800 Tue. If the task is assigned to a resource who works part-time,
having a calendar that shows his hours of work as 8am to 12 noon Mon thru
Fri, the same 3-day (1440 working time minute) task will start Mon 0800 and
end the following Monday at 12 noon, 7.5 actual elapsed ordinary
wall-calendar days later, each elapsed calendar day Mon through Fri only
'burning up' 240 working time minutes, thus requiring 2 sunrise-sunset days
to equal 1 working "day."

HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Mike" <Mike@discussions.microsoft.com> wrote in message
news:C45B12C6-6026-44AD-AC6B-CCF968B24E88@microsoft.com...
> Thanks for replying, Glen.
>
> We have a mix of resources where some of our equipment is run over a 24
> hour
> period, but the people and other equipment will be utilized within the
> standard 8 hours workday.
>
> If project can't handle the use of multiple calendars, then why does it
> know
> that the duration is 4 days when displaying the Gantt chart bars?
> Project's
> inability to handle multiple calendars comes as a shock and disappointment
> in
> what I would consider a pretty common scenario.
>
> Approaching the problem another way, if the calendar options were set so
> that "Hours per day" were 24 hours rather than the default 8 hours, would
> Project schedule tasks properly since working time of the 8-hour-per-day
> resources were restricted by their Standard calendars?
>
> --
>
> -Mike
>
>
> "Mike Glen" wrote:
>
>> Hi Mike,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> If all your work is on a 24 hour basis then you should change the working
>> hours: see FAQ Item: 5. Default Working Hours. However, I suspect this
>> is a
>> one-off and Project cannot handle effectively different calendars - it
>> has
>> to pick one to show - the standard project calendar based on an 8-hour
>> day
>> as you discovered. Don't forget that although the Duration shows 12.5
>> days,
>> the Work is correct at 100 hours. You'll have to live with that.
>>
>> FAQs, companion products and other useful Project information can be seen
>> at
>> this web address: http://project.mvps.org/faqs.htm
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>> See http://tinyurl.com/2xbhc for Project Tutorials
>>
>>
>>
>> "Mike" <Mike@discussions.microsoft.com> wrote in message
>> news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
>> >I have a Fixed Work task that will take 100 hours of Work. The resource
>> >is
>> >a
>> > piece of equipment that is allocated at 100% Units on the 24 Hours Base
>> > Calendar.
>> >
>> > The Duration, however, is calculated at 12.5 days in the Task view,
>> > which
>> > is
>> > what you'd expect for the Standard Base Calendar (8 hours/day). The
>> > Duration
>> > should be just over 4 days for this resource at 24 hours/day, which is
>> > how
>> > it
>> > appears in the Gantt chart (blue bar extends over a four day period).
>> >
>> > What could be causing this? Thanks.
>> >
>> >
>> > --
>> >
>> > -Mike
>>
>>
>>


Re: Duration Not Right When For a 24-hour Resource by Mike

Mike
Mon Mar 17 13:19:01 CDT 2008

Thanks for replying, Steve.

I believe what you're saying should produce the duration I'm expecting, i.e.
100h, or 6000 minutes, of Work broken up into (3) 8-hour (480-minute)
segments per day (as you've described) would result in a duration of just
over 4 days. Why am I seeing 12.5 days?

I must not be seeing the whole picture...

--

-Mike


"Steve House" wrote:

> It's not that Project can't use multiple calendars - it does so very nicely.
> The confusion arises when one forgets that duration is ALWAYS actually
> measured and calculated in units of working time minutes to the nearest
> 10th. In order to use more convenient units of days, weeks, months, etc,
> they have to be converted to and from minutes. The conversion factors
> applied are global within a project and independent of the working time
> calendar. With the default hours per day setting of 8
> (Tools/Options/Calendar) ANY time period of 480 minutes is considered a
> "day." The calendars, OTOH, determine WHICH minutes out of the 24-hour
> sunrise to sunrise day are to be considered working time. We enter a task
> with a duration of 3 days, ie, 1440 working time minutes, starting Monday @
> 8am. If the calendar governing that task is the standard 8-hour default
> calendar, those 3 480-minute "days" run 0800-1700 Mon, 0800-1700 Tue, and
> 0800-1700 Wed. On the other hand, if the 24-hour calendar is governing that
> task, those same 3 480-minute "days" run 0800-1600 Mon, 1600 Mon-0000 Tue,
> 0000-0800 Tue. If the task is assigned to a resource who works part-time,
> having a calendar that shows his hours of work as 8am to 12 noon Mon thru
> Fri, the same 3-day (1440 working time minute) task will start Mon 0800 and
> end the following Monday at 12 noon, 7.5 actual elapsed ordinary
> wall-calendar days later, each elapsed calendar day Mon through Fri only
> 'burning up' 240 working time minutes, thus requiring 2 sunrise-sunset days
> to equal 1 working "day."
>
> HTH
> --
> Steve House [Project MVP]
> MS Project Trainer & Consultant
> Visit http://project.mvps.org/faqs.htm for the FAQs
>
>
> "Mike" <Mike@discussions.microsoft.com> wrote in message
> news:C45B12C6-6026-44AD-AC6B-CCF968B24E88@microsoft.com...
> > Thanks for replying, Glen.
> >
> > We have a mix of resources where some of our equipment is run over a 24
> > hour
> > period, but the people and other equipment will be utilized within the
> > standard 8 hours workday.
> >
> > If project can't handle the use of multiple calendars, then why does it
> > know
> > that the duration is 4 days when displaying the Gantt chart bars?
> > Project's
> > inability to handle multiple calendars comes as a shock and disappointment
> > in
> > what I would consider a pretty common scenario.
> >
> > Approaching the problem another way, if the calendar options were set so
> > that "Hours per day" were 24 hours rather than the default 8 hours, would
> > Project schedule tasks properly since working time of the 8-hour-per-day
> > resources were restricted by their Standard calendars?
> >
> > --
> >
> > -Mike
> >
> >
> > "Mike Glen" wrote:
> >
> >> Hi Mike,
> >>
> >> Welcome to this Microsoft Project newsgroup :)
> >>
> >> If all your work is on a 24 hour basis then you should change the working
> >> hours: see FAQ Item: 5. Default Working Hours. However, I suspect this
> >> is a
> >> one-off and Project cannot handle effectively different calendars - it
> >> has
> >> to pick one to show - the standard project calendar based on an 8-hour
> >> day
> >> as you discovered. Don't forget that although the Duration shows 12.5
> >> days,
> >> the Work is correct at 100 hours. You'll have to live with that.
> >>
> >> FAQs, companion products and other useful Project information can be seen
> >> at
> >> this web address: http://project.mvps.org/faqs.htm
> >> Hope this helps - please let us know how you get on :)
> >>
> >> Mike Glen
> >> MS Project MVP
> >> See http://tinyurl.com/2xbhc for Project Tutorials
> >>
> >>
> >>
> >> "Mike" <Mike@discussions.microsoft.com> wrote in message
> >> news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
> >> >I have a Fixed Work task that will take 100 hours of Work. The resource
> >> >is
> >> >a
> >> > piece of equipment that is allocated at 100% Units on the 24 Hours Base
> >> > Calendar.
> >> >
> >> > The Duration, however, is calculated at 12.5 days in the Task view,
> >> > which
> >> > is
> >> > what you'd expect for the Standard Base Calendar (8 hours/day). The
> >> > Duration
> >> > should be just over 4 days for this resource at 24 hours/day, which is
> >> > how
> >> > it
> >> > appears in the Gantt chart (blue bar extends over a four day period).
> >> >
> >> > What could be causing this? Thanks.
> >> >
> >> >
> >> > --
> >> >
> >> > -Mike
> >>
> >>
> >>
>
>

Re: Duration Not Right When For a 24-hour Resource by Mike

Mike
Mon Mar 17 14:38:34 CDT 2008

Hi Mike,

Project does calculate and schedule taking into account all the calendars in
use, witness the correct Gantt Chart representation. What it does is to
represent the Duration in the table based on the number of hours in a day in
the project Standard calendar, declared in Project/Project Information. It
has to pick one calendar and that's the one Microsoft has chosen to use:
100hours at 8 hours/day = 12.5 days.

Mike Glen
Project MVP


Mike wrote:
> Thanks for replying, Glen.
>
> We have a mix of resources where some of our equipment is run over a
> 24 hour period, but the people and other equipment will be utilized
> within the standard 8 hours workday.
>
> If project can't handle the use of multiple calendars, then why does
> it know that the duration is 4 days when displaying the Gantt chart
> bars? Project's inability to handle multiple calendars comes as a
> shock and disappointment in what I would consider a pretty common
> scenario.
>
> Approaching the problem another way, if the calendar options were set
> so that "Hours per day" were 24 hours rather than the default 8
> hours, would Project schedule tasks properly since working time of
> the 8-hour-per-day resources were restricted by their Standard
> calendars?
>
>
>> Hi Mike,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> If all your work is on a 24 hour basis then you should change the
>> working hours: see FAQ Item: 5. Default Working Hours. However, I
>> suspect this is a one-off and Project cannot handle effectively
>> different calendars - it has to pick one to show - the standard
>> project calendar based on an 8-hour day as you discovered. Don't
>> forget that although the Duration shows 12.5 days, the Work is
>> correct at 100 hours. You'll have to live with that.
>>
>> FAQs, companion products and other useful Project information can be
>> seen at this web address: http://project.mvps.org/faqs.htm
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>> See http://tinyurl.com/2xbhc for Project Tutorials
>>
>>
>>
>> "Mike" <Mike@discussions.microsoft.com> wrote in message
>> news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
>>> I have a Fixed Work task that will take 100 hours of Work. The
>>> resource is a
>>> piece of equipment that is allocated at 100% Units on the 24 Hours
>>> Base Calendar.
>>>
>>> The Duration, however, is calculated at 12.5 days in the Task view,
>>> which is
>>> what you'd expect for the Standard Base Calendar (8 hours/day). The
>>> Duration
>>> should be just over 4 days for this resource at 24 hours/day, which
>>> is how it
>>> appears in the Gantt chart (blue bar extends over a four day
>>> period).
>>>
>>> What could be causing this? Thanks.
>>>
>>>
>>> --
>>>
>>> -Mike




Re: Duration Not Right When For a 24-hour Resource by Steve

Steve
Mon Mar 17 17:10:50 CDT 2008

If a "day" is defined as any 8-hour segment, a task that starts Monday at
8am and run continuously until Tuesday 8am will show "3 days" as the
duration in the Gantt chart task table even though in our normal world we
would say it's only 1 day. 24 hours / 8 hours per duration-day = 3
duration-days. Duration time is only loosely related to time as indicated
on the clock on the wall or tracked by conventional calendars such as your
day-planner. Think Star-Trek - the Enterprise used an Earth-standard day to
record time that bore no relation at all to the rotational period of the
planet they were visiting. In Project a 'standard-day' is defined as every
X working minutes, X being defined by the setting in Tools/Options/Calendar.
In your example, because work is proceeding 24/7, the number of working time
minutes between Monday 8am and Friday 12 noon IS the same as the number of
working time minutes in 12.5 standard 8-hour workdays, thus in duration days
the duration of that task is 12.5 days, not 4.25 even though the bar on the
graphic only covers four days + out of the week. There are 12.5 8-hour
segments between start and end, thus it is 12.5 days duration.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Mike" <Mike@discussions.microsoft.com> wrote in message
news:748A778C-30D9-4432-9340-48FBAAFFC7D9@microsoft.com...
> Thanks for replying, Steve.
>
> I believe what you're saying should produce the duration I'm expecting,
> i.e.
> 100h, or 6000 minutes, of Work broken up into (3) 8-hour (480-minute)
> segments per day (as you've described) would result in a duration of just
> over 4 days. Why am I seeing 12.5 days?
>
> I must not be seeing the whole picture...
>
> --
>
> -Mike
>
>
> "Steve House" wrote:
>
>> It's not that Project can't use multiple calendars - it does so very
>> nicely.
>> The confusion arises when one forgets that duration is ALWAYS actually
>> measured and calculated in units of working time minutes to the nearest
>> 10th. In order to use more convenient units of days, weeks, months, etc,
>> they have to be converted to and from minutes. The conversion factors
>> applied are global within a project and independent of the working time
>> calendar. With the default hours per day setting of 8
>> (Tools/Options/Calendar) ANY time period of 480 minutes is considered a
>> "day." The calendars, OTOH, determine WHICH minutes out of the 24-hour
>> sunrise to sunrise day are to be considered working time. We enter a
>> task
>> with a duration of 3 days, ie, 1440 working time minutes, starting Monday
>> @
>> 8am. If the calendar governing that task is the standard 8-hour default
>> calendar, those 3 480-minute "days" run 0800-1700 Mon, 0800-1700 Tue, and
>> 0800-1700 Wed. On the other hand, if the 24-hour calendar is governing
>> that
>> task, those same 3 480-minute "days" run 0800-1600 Mon, 1600 Mon-0000
>> Tue,
>> 0000-0800 Tue. If the task is assigned to a resource who works
>> part-time,
>> having a calendar that shows his hours of work as 8am to 12 noon Mon thru
>> Fri, the same 3-day (1440 working time minute) task will start Mon 0800
>> and
>> end the following Monday at 12 noon, 7.5 actual elapsed ordinary
>> wall-calendar days later, each elapsed calendar day Mon through Fri only
>> 'burning up' 240 working time minutes, thus requiring 2 sunrise-sunset
>> days
>> to equal 1 working "day."
>>
>> HTH
>> --
>> Steve House [Project MVP]
>> MS Project Trainer & Consultant
>> Visit http://project.mvps.org/faqs.htm for the FAQs
>>
>>
>> "Mike" <Mike@discussions.microsoft.com> wrote in message
>> news:C45B12C6-6026-44AD-AC6B-CCF968B24E88@microsoft.com...
>> > Thanks for replying, Glen.
>> >
>> > We have a mix of resources where some of our equipment is run over a 24
>> > hour
>> > period, but the people and other equipment will be utilized within the
>> > standard 8 hours workday.
>> >
>> > If project can't handle the use of multiple calendars, then why does it
>> > know
>> > that the duration is 4 days when displaying the Gantt chart bars?
>> > Project's
>> > inability to handle multiple calendars comes as a shock and
>> > disappointment
>> > in
>> > what I would consider a pretty common scenario.
>> >
>> > Approaching the problem another way, if the calendar options were set
>> > so
>> > that "Hours per day" were 24 hours rather than the default 8 hours,
>> > would
>> > Project schedule tasks properly since working time of the
>> > 8-hour-per-day
>> > resources were restricted by their Standard calendars?
>> >
>> > --
>> >
>> > -Mike
>> >
>> >
>> > "Mike Glen" wrote:
>> >
>> >> Hi Mike,
>> >>
>> >> Welcome to this Microsoft Project newsgroup :)
>> >>
>> >> If all your work is on a 24 hour basis then you should change the
>> >> working
>> >> hours: see FAQ Item: 5. Default Working Hours. However, I suspect
>> >> this
>> >> is a
>> >> one-off and Project cannot handle effectively different calendars - it
>> >> has
>> >> to pick one to show - the standard project calendar based on an 8-hour
>> >> day
>> >> as you discovered. Don't forget that although the Duration shows 12.5
>> >> days,
>> >> the Work is correct at 100 hours. You'll have to live with that.
>> >>
>> >> FAQs, companion products and other useful Project information can be
>> >> seen
>> >> at
>> >> this web address: http://project.mvps.org/faqs.htm
>> >> Hope this helps - please let us know how you get on :)
>> >>
>> >> Mike Glen
>> >> MS Project MVP
>> >> See http://tinyurl.com/2xbhc for Project Tutorials
>> >>
>> >>
>> >>
>> >> "Mike" <Mike@discussions.microsoft.com> wrote in message
>> >> news:82BD227C-A4F7-40C8-9867-4422C73B588B@microsoft.com...
>> >> >I have a Fixed Work task that will take 100 hours of Work. The
>> >> >resource
>> >> >is
>> >> >a
>> >> > piece of equipment that is allocated at 100% Units on the 24 Hours
>> >> > Base
>> >> > Calendar.
>> >> >
>> >> > The Duration, however, is calculated at 12.5 days in the Task view,
>> >> > which
>> >> > is
>> >> > what you'd expect for the Standard Base Calendar (8 hours/day). The
>> >> > Duration
>> >> > should be just over 4 days for this resource at 24 hours/day, which
>> >> > is
>> >> > how
>> >> > it
>> >> > appears in the Gantt chart (blue bar extends over a four day
>> >> > period).
>> >> >
>> >> > What could be causing this? Thanks.
>> >> >
>> >> >
>> >> > --
>> >> >
>> >> > -Mike
>> >>
>> >>
>> >>
>>
>>